Develop in Portugal
FAQ

Planning Timeline Estimator

Estimate planning steps and indicative timelines for your project.

Planning Timeline EstimatorToolsApp

Results

Total: 22–55 months

  1. 1. Land due diligence1–3 months
  2. 2. Pre-application / PIP2–4 months
  3. 3. Architectural project submission3–6 months
  4. 4. Licence and construction permit3–10 months
  5. 5. Construction11–27 months
  6. 6. Completion and use licence2–5 months

Assumptions

  • Durations are typical elapsed times, not statutory deadlines.
  • Municipal responsiveness varies widely and is the single biggest variable.
  • Third-party opinions, appeals and design revisions are not included.

Indicative ranges for early decisions only. Outcomes depend on the municipality, the PDM and the specific site. Not legal, tax or planning advice.

Your answers stay on this device. Nothing is uploaded and no account is needed.

Legal support through VVA

Want this checked properly?

Send the site and the scheme for a written legal and planning review before you commit.