Planning Timeline Estimator
Estimate planning steps and indicative timelines for your project.
Planning Timeline EstimatorToolsApp
Results
Total: 22–55 months
- 1. Land due diligence1–3 months
- 2. Pre-application / PIP2–4 months
- 3. Architectural project submission3–6 months
- 4. Licence and construction permit3–10 months
- 5. Construction11–27 months
- 6. Completion and use licence2–5 months
Assumptions
- Durations are typical elapsed times, not statutory deadlines.
- Municipal responsiveness varies widely and is the single biggest variable.
- Third-party opinions, appeals and design revisions are not included.
Indicative ranges for early decisions only. Outcomes depend on the municipality, the PDM and the specific site. Not legal, tax or planning advice.