Phase 04 of 08

Land & Project Acquisition

Acquiring development land or an existing project is more than agreeing a price. The buyer must confirm exactly what is being acquired, whether the intended development is realistically achievable, which liabilities accompany the transaction and what must happen before the acquisition becomes unconditional.

04Land & Project Acquisition

At a glance

Indicative duration
1–4 months
The decision
Should we acquire this property, company or project, and under what structure, conditions, price and risk allocation?
Documents
  • Land registry extract (certidão permanente) and tax record (caderneta predial).
  • Licence of use or proof of the current legal situation of any existing building.
  • CPCV with conditions precedent, deadlines and remedies.

The decision this phase helps you make

Should we acquire this property, company or project, and under what structure, conditions, price and risk allocation?

At the end of this phase, you should be able to decide:

  • what asset or rights you are acquiring;
  • whether to acquire the property or the property-owning company;
  • whether the acquisition should be immediate or conditional;
  • which risks must be resolved before completion;
  • which risks can be accepted, insured, priced or contractually allocated;
  • how the purchase price should be calculated and paid;
  • which deposits or guarantees are appropriate;
  • whether the seller can deliver the property or project in the agreed condition;
  • whether the project documents, approvals and intellectual property will be available after completion;
  • and whether the acquisition should proceed, be renegotiated or be abandoned.

A successful acquisition converts a development opportunity into a controlled asset. A poorly structured acquisition can convert planning, title, tax or construction uncertainty into an irreversible liability.

01What can be acquired?

A development transaction may involve more than the land itself.

1. Land or building acquisition

The buyer acquires ownership of the identified property directly from the registered owner.

The acquisition may concern:

  • undeveloped land;
  • a building requiring rehabilitation;
  • an operating property intended for conversion;
  • a partially completed development;
  • one or more units within a larger property;
  • a right of surface;
  • or another registrable property right.

The buyer must confirm that the property described in the contract corresponds to the land, boundaries, buildings and access points inspected on site.

+Show details(5)

2. Acquisition of a project company

Instead of acquiring the property, the buyer acquires shares or quotas in the company that owns the property.

This may preserve project contracts and operational continuity, but it also means that the buyer acquires a company with its history, liabilities, contractual obligations and potential undisclosed exposures.

  • A share acquisition therefore requires corporate, accounting, tax, employment, litigation and contractual due diligence in addition to the full property and planning review.

3. Acquisition of project rights

A buyer may acquire a package of contractual and project rights, such as:

  • architectural and engineering designs;
  • consultant appointments;
  • planning applications;
  • information requests or planning decisions;
  • construction contracts;
  • operator or management agreements;
  • marketing materials;
  • pre-sales arrangements;
  • warranties;
  • surveys and reports;
  • and rights under existing development agreements.

Not every project document, contract, licence or administrative position is automatically transferable. Assignment restrictions, third-party consents, intellectual-property ownership and administrative requirements must be checked individually.

4. Conditional acquisition

The buyer agrees to acquire the property only if defined conditions are satisfied.

Typical conditions may concern:

  • satisfactory legal, planning and technical due diligence;
  • confirmation of the development capacity;
  • obtaining a favourable planning decision;
  • rectification of boundaries or registered areas;
  • cancellation of mortgages or attachments;
  • delivery of the property free from occupants;
  • non-exercise of applicable pre-emption rights;
  • financing approval;
  • corporate approvals;
  • or delivery of specified project documents.

The condition must be objectively drafted. The contract should identify who is responsible for satisfying it, the evidence required, the deadline, any right of waiver and what happens if the condition is not satisfied.

5. Option to acquire

An option can give the investor the right, but not the obligation, to acquire the property within an agreed period and under defined conditions.

An option may be useful when the investor needs time to:

  • investigate development potential;
  • obtain a planning decision;
  • assemble adjoining plots;
  • arrange financing;
  • secure an operator;
  • or complete commercial negotiations.

The option document must define the asset, price or pricing formula, option period, exercise mechanism, exclusivity, access rights, option fee and consequences of expiry.

6. Landowner joint venture

Instead of selling the property immediately, the landowner may contribute land or grant development rights to a joint project.

The developer may contribute:

  • capital;
  • project management;
  • design and licensing work;
  • financing arrangements;
  • construction management;
  • and sales or operational expertise.

The agreement must address control, funding, decision-making, land valuation, security, cost overruns, distributions, deadlock, default, dilution and exit. A joint venture does not eliminate acquisition risk. It changes how that risk is shared and governed.

02Choose the acquisition structure before negotiating the document

The commercial route should be selected before the parties begin drafting the definitive transaction documents.

The structure should be reviewed jointly by legal, tax, planning and financial advisers. A transaction that appears simpler from a legal perspective may produce a less efficient tax or financing result, and the reverse may also be true.

Direct asset purchase

The buyer acquires:

  • The property or another registrable property right.
  • Main advantage: clearer separation from the seller’s corporate history.
  • Main risk: transfer taxes, title issues and project-right transfer requirements.
+Show details(5)

Share purchase

The buyer acquires:

  • The company that owns the property.
  • Main advantage: operational and contractual continuity may be preserved.
  • Main risk: historical and undisclosed company liabilities.

Conditional purchase

The buyer acquires:

  • The property after defined conditions are satisfied.
  • Main advantage: limits exposure to identified development risks.
  • Main risk: conditions may be disputed if drafted subjectively.

Option

The buyer acquires:

  • A right to acquire during an agreed period.
  • Main advantage: allows investigation before committing to purchase.
  • Main risk: protection depends on enforceability, duration and contractual structure.

Landowner joint venture

The buyer acquires:

  • Contractual or corporate participation in the project.
  • Main advantage: reduces the immediate land acquisition cost.
  • Main risk: governance, funding and exit disputes.

Project-rights acquisition

The buyer acquires:

  • Designs, applications, contracts and other project assets.
  • Main advantage: may accelerate an existing project.
  • Main risk: rights and approvals may be incomplete or non-transferable.

03Before making an offer

An offer should be based on clearly stated assumptions.

Before issuing a letter of intent, heads of terms or commercial offer, define:

The exact transaction perimeter

Identify:

  • the property or properties;
  • the registered description;
  • the tax registration;
  • the physical boundaries;
  • included buildings and infrastructure;
  • access and parking;
  • project documents;
  • intellectual property;
  • contracts;
  • licences and applications;
  • movable equipment;
  • receivables or liabilities;
  • and any property or right that is specifically excluded.
+Show details(5)

The proposed structure

State whether the transaction is intended to be:

  • an asset purchase;
  • a share purchase;
  • a project-rights purchase;
  • an option;
  • a promissory purchase agreement;
  • a joint venture;
  • or another conditional arrangement.

The structure should remain subject to legal and tax confirmation until the relevant due diligence has been completed.

The price assumptions

Clarify whether the price is:

  • fixed;
  • calculated by registered area;
  • calculated by verified site area;
  • linked to permitted construction area;
  • adjusted by planning outcome;
  • subject to completion accounts;
  • partly deferred;
  • or supplemented by an overage or earn-out.

Terms such as “construction area”, “gross floor area”, “saleable area” and “approved area” must be defined. Different documents and professionals may use these expressions differently.

The due diligence period

The buyer should have sufficient time and access to:

  • inspect the property;
  • review the complete data room;
  • commission surveys;
  • meet the project team;
  • verify planning information;
  • and raise follow-up questions.

The timetable should begin only when the agreed minimum information has been delivered.

Exclusivity

Exclusivity should define:

  • its duration;
  • the properties and transaction covered;
  • prohibited seller conduct;
  • whether existing negotiations must be disclosed or terminated;
  • the seller’s duty to cooperate;
  • permitted communications;
  • extensions;
  • and remedies for breach.

A short exclusivity period with an incomplete data room may provide little real protection.

Binding and non-binding provisions

A letter of intent or heads of terms may be described as non-binding while containing binding provisions on:

  • confidentiality;
  • exclusivity;
  • access;
  • costs;
  • governing law;
  • dispute resolution;
  • announcements;
  • and return or destruction of information.

The legal effect depends on the wording and circumstances, not only on the title of the document.

04Acquisition due diligence

Due diligence should verify the assumptions supporting the price, financing and development programme.

It is not enough to identify risks. The team must determine how each material risk will be:

  • resolved before completion;
  • accepted by the buyer;
  • reflected in the price;
  • covered by a warranty or indemnity;
  • secured by a retention or guarantee;
  • insured;
  • or treated as a reason not to proceed.

1. Ownership and title

Confirm:

  • the registered owner;
  • the seller’s authority to sell;
  • the property description;
  • pending registrations;
  • mortgages;
  • attachments;
  • usufructs;
  • surface rights;
  • easements;
  • rights of way;
  • options;
  • pre-emption rights;
  • restrictions on disposal;
  • and any conflicting registered rights.

The permanent land registry certificate provides current information on the registered legal status of the property. It should be checked again immediately before completion. A land registry record does not replace physical, cadastral and topographical verification.

+Show details(9)

2. Boundaries, area and cadastral consistency

Compare:

  • the land registry;
  • the tax register;
  • cadastral information;
  • topographical surveys;
  • municipal plans;
  • existing project drawings;
  • and the physical occupation of the site.

Investigate:

  • inconsistent areas;
  • unclear boundaries;
  • overlaps;
  • unregistered buildings;
  • informal access;
  • occupation by neighbours;
  • shared infrastructure;
  • and discrepancies between documents and the site.

A price linked to area should state which measurement controls and what happens if the verified area differs from the stated area.

3. Access and infrastructure

Confirm legally enforceable access to a public road and the practical availability of:

  • water;
  • sewage;
  • electricity;
  • telecommunications;
  • drainage;
  • waste services;
  • and any infrastructure required by the intended project.

Physical access does not necessarily establish a legal right of access. The acquisition documents should address any easements, infrastructure agreements, municipal works or off-site improvements required for the project.

4. Planning and licensing

Review:

  • applicable territorial plans;
  • land classification and qualification;
  • planning constraints;
  • information requests and responses;
  • approved designs;
  • licences;
  • prior communications;
  • conditions imposed by authorities;
  • use documentation;
  • infrastructure obligations;
  • fees;
  • expiry dates;
  • pending amendments;
  • administrative proceedings;
  • and correspondence with the municipality and other authorities.

For an existing project, confirm:

  • what was actually approved;
  • whether the approved design matches the current business plan;
  • whether the approval or procedure remains effective;
  • whether deadlines have been met;
  • whether conditions remain outstanding;
  • whether changes of ownership or project team require action;
  • and whether the buyer will have lawful access to all drawings and technical files.

Never price an acquisition solely on the seller’s statement that a project is “approved”.

5. Physical and technical condition

Depending on the asset, commission appropriate investigations covering:

  • topography;
  • geotechnical conditions;
  • structural condition;
  • contamination;
  • asbestos or hazardous materials;
  • utilities;
  • flood and fire exposure;
  • demolition;
  • archaeology;
  • trees and protected habitats;
  • existing buildings;
  • construction defects;
  • and incomplete works.

The contractual remedy should reflect the risk. A report identifying a problem does not itself protect the buyer.

6. Occupation and third-party rights

Identify all persons using or occupying the property, including:

  • tenants;
  • licensees;
  • operators;
  • caretakers;
  • contractors;
  • neighbouring owners;
  • agricultural users;
  • and informal occupants.

Review:

  • leases;
  • licences;
  • management agreements;
  • concessions;
  • temporary occupation arrangements;
  • and other rights that may survive completion or delay possession.

If vacant possession is required, define what “vacant” means, who must deliver it and the evidence required at completion.

7. Existing project contracts

Review all material contracts, including:

  • architectural and engineering appointments;
  • planning consultancy agreements;
  • contractor appointments;
  • project-management agreements;
  • operator or franchise agreements;
  • brokerage and marketing agreements;
  • pre-sales;
  • reservation agreements;
  • utility agreements;
  • insurance;
  • financing documents;
  • and litigation settlements.

Confirm whether each contract will:

  • remain in force;
  • be terminated;
  • be assigned;
  • be novated;
  • require consent;
  • or be replaced.

8. Intellectual property and project information

Ownership of the land does not automatically give the buyer unrestricted rights to use, alter or reproduce every design prepared for the project.

Confirm rights to:

  • architectural drawings;
  • engineering designs;
  • BIM and digital files;
  • surveys;
  • renders;
  • branding;
  • marketing materials;
  • specifications;
  • reports;
  • and databases.

The buyer should receive the editable source files and not only PDF copies where continued project development requires them.

9. Tax position

For an asset acquisition, review:

  • Property Transfer Tax, known as IMT;
  • Stamp Duty;
  • any applicable VAT treatment;
  • annual property taxation;
  • tax values;
  • exemptions or benefits;
  • municipal charges;
  • and the tax consequences of the intended ownership and development structure.

The applicable IMT rate and taxable base depend on the property, use, value, parties and transaction structure. A universal rate should not be assumed.

A share acquisition does not automatically avoid IMT. Under the Portuguese IMT Code, an acquisition of shares or quotas may be treated as a taxable property transfer when the statutory conditions are cumulatively met, including conditions relating to the company’s property assets and the level of ownership or control acquired.

Tax analysis should be completed before the transaction structure becomes binding. See the Portuguese Tax Authority’s IMT Code — Article 2.

10. Corporate due diligence in a share acquisition

When acquiring a property-owning company, review:

  • commercial registration;
  • articles of association;
  • shareholders or quota holders;
  • beneficial ownership;
  • corporate approvals;
  • annual accounts;
  • management accounts;
  • tax returns;
  • financing;
  • shareholder loans;
  • guarantees;
  • employment;
  • social-security compliance;
  • litigation;
  • insurance;
  • related-party transactions;
  • distributions;
  • contracts;
  • data protection;
  • and regulatory compliance.

The buyer should also establish whether a change of control:

  • requires consent;
  • triggers termination rights;
  • accelerates debt;
  • affects a licence;
  • or breaches an operator, finance or development agreement.

A permanent commercial certificate gives access to current registered information and pending commercial registration requests. The RCBE identifies the natural persons declared as ultimately controlling the entity, but RCBE information does not itself constitute proof of the entity’s legal status.

05Asset purchase or share purchase?

The correct answer is project-specific.

The decision should reflect:

  • tax;
  • financing;
  • historical liabilities;
  • project contracts;
  • administrative position;
  • seller profile;
  • intended exit;
  • timing;
  • and the buyer’s risk tolerance.

Direct asset purchase

In an asset purchase, the buyer can define the specific property and project assets being acquired.

This generally provides clearer separation from the seller’s unrelated corporate liabilities. However, the buyer must address:

  • property transfer taxes;
  • formal transfer requirements;
  • registration;
  • assignment of contracts;
  • transfer or continued use of project documentation;
  • and any consents required for the project.

Share purchase

In a share purchase, the property remains within the acquired company.

Contracts, permits and operational relationships may remain with the same entity, subject to change-of-control provisions and applicable law. However, known and unknown liabilities remain in that company. Share purchase protection commonly includes:

  • warranties;
  • tax covenants;
  • specific indemnities;
  • disclosure;
  • price retention;
  • escrow;
  • guarantees;
  • completion accounts;
  • and limitations on liability.

These protections are valuable only if properly drafted, financially supported and enforceable against a seller with the capacity to meet a future claim.

A lower headline price or apparent tax saving should not determine the structure without a complete comparison of the resulting risks.

06Reservation, exclusivity, option or promissory agreement?

These documents perform different functions.

Reservation agreement

A reservation may temporarily remove the property from the market, but there is no universal legal meaning or standard refund regime for a “reservation fee”. The agreement must specify:

  • what is being reserved;
  • for how long;
  • whether the property can still be marketed;
  • whether the payment is refundable;
  • who holds the payment;
  • when it may be released;
  • and what happens if the parties do not sign a later agreement.
+Show details(3)

Exclusivity agreement

Exclusivity prevents specified negotiations or transactions during an agreed period. It does not necessarily oblige the buyer to acquire the property or the seller to complete the sale.

It should provide enough time and cooperation for the proposed investigation.

Option agreement

An option may give the buyer a unilateral right to proceed with the acquisition during a defined period.

The exercise procedure must be unambiguous. The agreement should also address registration or other protective measures where appropriate and legally available.

Promissory purchase and sale agreement

A Portuguese promissory agreement, commonly referred to as a CPCV, creates an obligation to enter into the future definitive contract on the agreed terms.

It should not be treated as a simple reservation document. Portuguese law imposes form requirements on promissory agreements, with additional requirements potentially applying to promises concerning buildings or urban units. The form and execution method should be confirmed for the specific transaction. The agreement should address:

  • exact identification of the parties and property;
  • purchase price;
  • payments;
  • conditions precedent;
  • completion date or mechanism;
  • long-stop date;
  • seller cooperation;
  • access;
  • title and encumbrances;
  • possession;
  • public and private pre-emption rights;
  • project documents;
  • representations;
  • allocation of taxes and costs;
  • assignment;
  • default;
  • contractual remedies;
  • specific performance;
  • termination;
  • and dispute resolution.

Under the Portuguese Civil Code, amounts paid by a promissory purchaser to the promissory seller are generally presumed to constitute a deposit or “sinal”. Depending on the circumstances, contractual wording and party responsible for non-performance, the statutory consequences can include loss of the amount paid or a claim for double its amount. The deposit, default and remedy provisions must therefore be deliberately drafted. Do not assume that a payment is refundable merely because the transaction has not completed. See the Portuguese Civil Code, including Articles 410 to 413 and 440 to 442.

07Conditions precedent

A condition precedent determines whether completion is required. It is not the same as a general statement that the transaction remains “subject to due diligence”.

Each condition should identify:

  • the required outcome;
  • the responsible party;
  • the applicable standard;
  • the documents or evidence required;
  • the deadline;
  • the obligation to cooperate;
  • whether it may be waived;
  • who may waive it;
  • the consequences of non-satisfaction;
  • and what happens to amounts already paid.

Satisfactory title

Confirmation that the seller has the required title and can transfer the property free from specified encumbrances.

+Show details(7)

Planning outcome

A favourable planning decision meeting objectively defined parameters, such as use, gross construction area, number of units, height, parking, access and infrastructure obligations.

Avoid vague conditions based only on obtaining “approval”. An approval materially different from the investment case may have little commercial value.

Area and boundaries

Confirmation of minimum site area, agreed boundaries and absence of material overlaps or occupations.

Release of security

Cancellation of mortgages, attachments or other charges at or before completion, using a coordinated release and payment mechanism.

Vacant possession

Delivery of the property without occupants, leases, licences, materials or equipment not accepted by the buyer.

Pre-emption rights

Evidence that applicable statutory or contractual pre-emption procedures have been completed without the right being exercised.

Public pre-emption rights can apply, for example, to certain classified properties and properties in protected areas or urban rehabilitation areas. The specific property and transaction must be checked. See the official Casa Pronta pre-emption service.

Project documents and consents

Delivery or valid transfer of agreed designs, reports, contracts, warranties and intellectual-property rights, together with any required third-party consents.

Financing

Where completion depends on financing, the contract should specify whether financing is a condition, how it is evidenced and whether the buyer must use reasonable efforts to obtain it.

Sellers may resist a broad financing condition. This risk should be negotiated expressly and not left to assumption.

08Price and payment structures

The price mechanism should match the remaining uncertainty.

Fixed price

The purchase price is agreed and does not change unless a specified contractual adjustment applies.

This is simple, but the buyer assumes the risk that the development potential or measured area differs from its expectations unless protected by conditions, warranties or termination rights.

+Show details(5)

Area-based adjustment

The price is adjusted by reference to verified land area, approved construction area or another defined measurement. The agreement must specify:

  • the measurement standard;
  • the responsible surveyor;
  • the controlling document;
  • permitted tolerance;
  • dispute procedure;
  • and any minimum or maximum adjustment.

Planning-linked price

Part of the price depends on the planning outcome.

The formula should define the relevant approval, area, use, date and calculation method. It should also address later amendments, phased approvals and appeals.

Deferred consideration

Part of the price is paid after completion.

The documents should address:

  • payment dates;
  • conditions;
  • interest;
  • security;
  • set-off;
  • subordination to lenders;
  • and dispute mechanisms.

Overage or earn-out

The seller may receive an additional payment if the project later achieves an agreed planning, construction, sales or operational outcome.

Long-term overage provisions require precise definitions, reporting obligations, audit rights, security and clear rules governing changes to the project.

Share-deal price adjustments

A share acquisition may use:

  • a fixed or locked-box price;
  • completion accounts;
  • adjustments for cash, debt and working capital;
  • or specific deductions for identified liabilities.

The property value and the equity purchase price are not necessarily the same figure.

09Deposits, escrow and transaction security

Before transferring money, establish the legal nature of the payment and the protection it provides.

Possible protections include:

  • a stakeholder arrangement;
  • escrow;
  • bank guarantee;
  • parent-company guarantee;
  • purchase-price retention;
  • holdback;
  • warranty and indemnity insurance;
  • or direct discharge of seller debt from the completion funds.

Before transferring money, establish:

  • the legal nature of the payment;
  • who receives or holds it;
  • whether it constitutes “sinal”;
  • permitted release conditions;
  • refund circumstances;
  • default consequences;
  • insolvency exposure;
  • and whether any guarantee, retention or escrow arrangement is required.

Not every mechanism is appropriate or available for every transaction. The protection must match the identified risk and remain enforceable after completion.

10Financing the acquisition

The finance plan should be coordinated with the transaction timetable.

Confirm:

  • the borrowing entity;
  • equity commitments;
  • lender due diligence;
  • valuation;
  • security;
  • conditions precedent;
  • guarantees;
  • intercreditor arrangements;
  • permitted development expenditure;
  • and any restrictions on distributions or asset disposals.

Where the seller’s property is mortgaged

The completion process should coordinate:

  • confirmation of the secured debt;
  • lender instructions;
  • allocation of the completion funds;
  • delivery of cancellation documents;
  • execution of the acquisition title;
  • registration of the buyer’s acquisition;
  • and registration of the new lender’s security, where applicable.

The buyer should not rely on an informal assurance that the mortgage will be removed after completion.

11Signing and completion

Signing and completion may occur on the same date or at different times.

At signing

The parties agree the binding transaction terms and, where applicable, begin the process for satisfying conditions precedent. The buyer should know precisely:

  • what becomes binding;
  • what payments are due;
  • what can still prevent completion;
  • who carries the property risk;
  • whether the seller may continue operating or altering the project;
  • and which conduct is restricted before completion.
+Show details(4)

Between signing and completion

The agreement may regulate:

  • maintenance of the property;
  • new leases or contracts;
  • project amendments;
  • financing;
  • distributions;
  • litigation settlements;
  • communication with authorities;
  • access by the buyer;
  • insurance;
  • and preservation of project information.

In a share acquisition, these interim controls are especially important because the value and liabilities of the target company may change before completion.

At completion of an asset acquisition

The parties should confirm:

  • execution of the legally required transfer instrument;
  • payment of the applicable taxes;
  • payment of the balance of the price;
  • cancellation or controlled discharge of security;
  • delivery of possession;
  • delivery of original and digital project records;
  • satisfaction of pre-emption procedures;
  • and submission of the acquisition and related security for registration.

Portuguese property transactions may be completed through a public deed, an authenticated private document or an integrated registration service such as Casa Pronta, depending on the transaction and chosen procedure. An authenticated private document used for property registration must comply with the applicable authentication and electronic-deposit requirements. See the Justice portal guidance on authenticated private documents.

At completion of a share acquisition

The parties should address:

  • transfer instruments;
  • corporate approvals;
  • resignations and appointments;
  • company books;
  • commercial registrations;
  • bank mandates;
  • shareholder loans;
  • releases;
  • beneficial-ownership information;
  • original records;
  • and control of the company’s accounts, systems and documents.

After completion

Post-completion actions may include:

  • definitive property or commercial registrations;
  • beneficial-ownership updates;
  • tax reporting;
  • municipal notifications;
  • insurance updates;
  • utility transfers;
  • contractor or consultant novations;
  • finance drawdown requirements;
  • and implementation of the next planning and design phase.

Property acquisition is subject to mandatory registration. The registration publicises the new ownership and protects the parties’ legal position. See the IRN guidance on definitive acquisition registration.

12Indicative transaction sequence

The acquisition process typically follows these steps.

Step 1 — Initial screening

Confirm that the opportunity meets the buyer’s location, use, scale, return and timing criteria.

+Show details(8)

Step 2 — Preliminary structure and offer

Select the provisional transaction structure and issue a carefully qualified offer or heads of terms.

Step 3 — Exclusivity and data room

Secure an appropriate investigation period and obtain the agreed documentation.

Step 4 — Due diligence

Complete the legal, planning, technical, environmental, tax, financial and commercial review.

Step 5 — Risk allocation

Decide which risks must be resolved, priced, insured, secured or accepted.

Step 6 — Transaction documents

Negotiate the option, CPCV, sale and purchase agreement, joint-venture agreement or other definitive documentation.

Step 7 — Conditions precedent

Obtain the required planning decisions, consents, releases, financing and other evidence.

Step 8 — Completion

Execute the required documents, pay the applicable amounts, transfer control or possession and submit the necessary registrations.

Step 9 — Post-completion implementation

Complete the outstanding registrations, transfer project information and move into planning, design or construction.

13Indicative timing

Acquisition timing depends on the asset, transaction structure, quality of the seller’s data room and conditions precedent.

As an initial planning assumption:

  • preliminary negotiations and heads of terms: 1–3 weeks;
  • data-room preparation and due diligence: 4–10 weeks;
  • transaction-document negotiation: often runs in parallel with due diligence;
  • satisfaction of non-planning conditions: 2–8 weeks;
  • planning-dependent conditional period: several months or longer;
  • completion preparation after satisfaction of conditions: 1–3 weeks.

A straightforward acquisition may complete within one to three months. A complex project, share acquisition, title rectification, planning condition or multi-party joint venture may require six months or significantly longer. These periods are indicative only and should not be treated as statutory deadlines.

14Acquisition cost categories

The acquisition budget should include more than the purchase price.

Allow for:

  • IMT;
  • Stamp Duty;
  • any applicable VAT;
  • registration and authentication costs;
  • legal advisers;
  • tax advisers;
  • planning consultants;
  • architects and engineers;
  • topographical and cadastral surveys;
  • structural and geotechnical investigations;
  • environmental investigations;
  • valuation;
  • lender costs;
  • insurance;
  • company incorporation or restructuring;
  • finance arrangement costs;
  • and contingency for rectification work.

The tax and transaction-cost estimate should be prepared for the actual property, buyer, structure and intended use. Generic online calculations should be treated as preliminary indications only.

15Documents and evidence

The acquisition file should contain:

Organise the following records:

  • transaction perimeter and excluded assets;
  • structure decision and tax analysis;
  • title, registry and tax certificates;
  • boundary and area verification;
  • access and infrastructure assessment;
  • planning and licensing review;
  • technical and environmental reports;
  • occupation and lease review;
  • project contract and IP review;
  • corporate due diligence for share acquisitions;
  • conditions-precedent matrix;
  • price and adjustment mechanism;
  • deposit and security arrangements;
  • financing and security terms;
  • completion checklist;
  • post-completion action plan.

Acquisition decision gate

Proceed only when the investment committee or decision-makers can answer “yes” to the following questions:

  • Asset — Do we know exactly what property, company and project rights are being acquired?
  • Asset — Do the registered, tax, cadastral and physical descriptions materially align?
  • Asset — Is access legally and physically adequate?
  • Development — Is the development case supported by planning evidence?
  • Development — Are the required uses, areas and infrastructure assumptions realistic?
  • Development — Have existing approvals and project files been independently verified?
  • Risk — Have material title, planning, technical, environmental, tax and corporate risks been identified?
  • Risk — Is each material risk resolved or contractually allocated?
  • Risk — Are the seller’s warranties and indemnities financially meaningful?
  • Contract — Are the conditions precedent objective and enforceable?
  • Contract — Are deposit and default consequences understood?
  • Contract — Can the buyer terminate or adjust the price if critical assumptions fail?
  • Contract — Is there a workable completion and registration process?
  • Finance — Is the total acquisition and development funding available?
  • Finance — Have transfer taxes and transaction costs been included?
  • Finance — Can existing security be discharged and new security registered safely?
  • Delivery — Will the buyer receive possession, contracts, designs, source files and project records?
  • Delivery — Can the project proceed immediately after completion?
  • Delivery — Are all post-completion responsibilities assigned?

If any critical answer remains uncertain, the acquisition should remain conditional or be renegotiated.

Red flags at this phase

  • Acquiring before completing development due diligence.
  • Assuming a planning statement is an approval.
  • Using vague conditions precedent.
  • Paying a reservation amount without defining its legal nature.
  • Treating the CPCV as an informal document.
  • Assuming a share deal avoids property transfer tax.
  • Reviewing the property but not the project company.
  • Ignoring public or private pre-emption rights.
  • Assuming project contracts and designs automatically transfer.
  • Completing before seller security is released.
  • Confusing physical possession with legal ownership.
  • Failing to control the period between signing and completion.

Indicative timing and costs

Acquisition timing depends on the asset, transaction structure, quality of the seller’s data room and conditions precedent.

A straightforward acquisition may complete within one to three months. A complex project, share acquisition, title rectification, planning condition or multi-party joint venture may require six months or significantly longer.

  1. preliminary negotiations and heads of terms: 1–3 weeks;
  2. data-room preparation and due diligence: 4–10 weeks;
  3. transaction-document negotiation: often runs in parallel with due diligence;
  4. satisfaction of non-planning conditions: 2–8 weeks;
  5. planning-dependent conditional period: several months or longer;
  6. completion preparation after satisfaction of conditions: 1–3 weeks.

These periods are indicative only and should not be treated as statutory deadlines. The acquisition budget should include the purchase price, IMT, Stamp Duty, VAT where applicable, registration and authentication costs, professional fees, surveys, investigations, lender costs, insurance and contingency.

Common acquisition mistakes

  1. 1Acquiring before completing development due diligence.
  2. 2Assuming a planning statement is an approval.
  3. 3Using vague conditions precedent.
  4. 4Paying a reservation amount without defining its legal nature.
  5. 5Treating the CPCV as an informal document.
  6. 6Assuming a share deal avoids property transfer tax.
  7. 7Reviewing the property but not the project company.
  8. 8Ignoring public or private pre-emption rights.
  9. 9Assuming project contracts and designs automatically transfer.
  10. 10Completing before seller security is released.
  11. 11Confusing physical possession with legal ownership.
  12. 12Failing to control the period between signing and completion.

Acquisition readiness checklist

Before signing a binding acquisition agreement, confirm that you have:

Progress: 0/26

Progress is saved in this browser only.

Frequently asked questions

Should I buy the land before obtaining planning confirmation?

Not necessarily. Where development capacity is uncertain, an option or conditional acquisition may allow the buyer to investigate or obtain a planning decision before becoming unconditionally obliged to acquire. The seller may require a fee, deposit, timetable or minimum planning parameters in return for accepting this structure.

Is a CPCV always required?

No. The parties may proceed directly to the definitive acquisition or use another transaction structure. However, a CPCV is commonly used when there is a period between agreement of the commercial terms and completion. Whether it is appropriate depends on the due diligence, financing, planning and timing requirements.

Is every amount paid under a CPCV refundable?

No. Amounts paid by the promissory buyer may be presumed to constitute “sinal” under Portuguese law. The contract and applicable legal regime determine the consequences of termination or default. Refund rights must be expressly reviewed before payment.

Does a CPCV transfer ownership?

No. A CPCV generally creates an obligation to enter into the future definitive contract. Ownership must be transferred using the legally required form and the acquisition must be submitted for registration.

Is a share purchase safer than buying the property?

Not automatically. A share purchase may preserve the project company’s contracts and administrative continuity, but the buyer acquires the company with its historical liabilities. The correct structure depends on full property, corporate and tax due diligence.

Does a share purchase avoid IMT?

Not necessarily. Portuguese tax law can treat certain acquisitions of shares or quotas in property-owning entities as taxable transfers when the statutory conditions are satisfied. Obtain transaction-specific tax advice before selecting the structure.

Can I rely on the area in the land registry or tax record?

Not without comparison. Registered, tax, cadastral, topographical and physical areas may differ. Material discrepancies should be investigated and, where necessary, corrected or addressed in the price and conditions precedent.

Do existing planning approvals automatically benefit the buyer?

Do not assume that they do. The buyer should verify the nature, scope, validity, deadlines and conditions of each procedure or approval, as well as any requirements linked to the applicant, property owner, project team or transfer of project documents.

Can the seller continue changing the project after signing?

Only to the extent permitted by the agreement. Where signing and completion are separated, the contract should regulate changes to the property, company, designs, contracts, financing and applications.

Can a foreign investor acquire Portuguese development property?

Foreign individuals and companies can generally invest in Portuguese real estate, but the acquisition remains subject to Portuguese property, tax, registration, anti-money-laundering and source-of-funds requirements, as well as any rules applicable to the particular investor, asset or activity. The ownership and financing structure should be established before signing.

Tools for this phase

Project Due Diligence Checklist

Organise legal, planning, technical, environmental, tax and corporate investigations.

Build your due diligence list

Development Cost Planner

Estimate purchase price, taxes, professional costs, finance costs and contingency.

Build an acquisition budget

Personal Development Plan

Create a structured list of acquisition conditions, responsible parties, evidence and deadlines.

Define your conditions

Next phase

05 — Planning & Design

Transform the acquisition case into a coordinated planning, architectural and technical project.

Continue to Planning & Design

Legal support through VVA

VVA can support investors, developers, family offices, funds and operators throughout the acquisition of development land, existing buildings and property-owning companies in Portugal.

Legal services are provided by Valente Veiga & Associados.

Official sources

  • Portuguese Civil Code — consolidated version.
  • Decree-Law 116/2008 — property transaction and registration formalities.
  • Casa Pronta property transaction service.
  • Permanent land registry certificate.
  • Definitive acquisition registration.
  • Authenticated private property documents.
  • Public pre-emption procedure.
  • Permanent commercial certificate.
  • Central Register of Beneficial Ownership.
  • Portuguese IMT Code — Article 2.
  • Portuguese IMT Code — Article 22.

Last reviewed: 21 August 2026

This page provides general information about development acquisitions in Portugal. It does not constitute legal, tax, planning, technical, investment or financial advice. Applicable rules, procedures, taxes and contractual outcomes depend on the property, municipality, parties, transaction structure and facts of each project. Obtain project-specific professional advice before signing any reservation, exclusivity, option, promissory, purchase, financing, joint-venture or development agreement.