Phase 01 of 08

Development strategy

A development strategy defines what you intend to build, who it is for, how it will be funded and what a successful outcome should look like.

01Development strategy

At a glance

Indicative duration
2–6 weeks
The decision
What type of development should we pursue, where should we pursue it and under what commercial, legal and financial limits?
Documents
  • A one-page investment thesis with target return and capital limit.
  • An outline development brief for the architect.
  • A shortlist of two or three regions with a reason for each.

The decision this phase helps you make

What type of development should we pursue, where should we pursue it and under what commercial, legal and financial limits?

By the end of this phase, the developer should be able to explain:

  • the intended project type;
  • the target customer, tenant, guest or operator;
  • the locations that fit the strategy;
  • the preferred development and acquisition model;
  • the approximate scale;
  • the available capital;
  • the minimum commercial outcome;
  • the principal risks the developer will accept;
  • the risks that will cause the project to be rejected;
  • the intended sale, holding, operation or exit route.

The result should be a written project brief that can be used by the internal team and external advisers.

01Why strategy comes before the site

A site is not an investment strategy.

The same property may support several theoretically possible projects, but those projects can have very different:

  • customers;
  • planning requirements;
  • design efficiencies;
  • infrastructure needs;
  • construction costs;
  • funding profiles;
  • operating obligations;
  • sales periods;
  • risk levels;
  • exit routes.

A low land price does not necessarily mean that the site is attractive. It may reflect limited demand, infrastructure requirements, planning restrictions, difficult ground conditions, title issues or a use for which there is little commercial market.

Equally, an expensive site may be viable if it has a sufficiently clear planning position, strong demand, an efficient design, reliable infrastructure and a realistic route to sale or operation.

The strategic question is not simply: is this land cheap or expensive?

It is: can this site deliver the product, return and exit required by the strategy after allowing for planning, time, cost, finance and risk?

021. Define the product

The initial product definition should be specific enough to guide site selection without becoming a fixed architectural design.

Possible development models include:

  • residential units for individual sale;
  • houses or villas for sale;
  • urban rehabilitation;
  • build-to-rent;
  • student accommodation;
  • senior living;
  • co-living;
  • hotels;
  • aparthotels;
  • tourist apartments;
  • tourist resorts;
  • branded residences;
  • mixed-use development;
  • land subdivision and serviced plots;
  • logistics or industrial development;
  • acquisition and completion of an existing project.

The product definition should address:

  • intended use;
  • target customer;
  • approximate unit, room or plot count;
  • positioning and specification;
  • required amenities;
  • parking;
  • outdoor areas;
  • operational requirements;
  • sustainability and energy objectives;
  • likely sale, rent or room-rate positioning;
  • expected delivery period.

The intended commercial description must be compatible with the legal and planning use. Marketing terminology does not determine the applicable planning, tourism, residential or operational regime. Expressions such as “serviced apartments”, “branded residences” or “resort residences” may describe a commercial product, but they do not, by themselves, establish the lawful use or the applicable legal framework.

032. Identify the customer

The project should be designed around a defined customer or user rather than a general assumption that demand exists.

The target may include:

  • local owner-occupiers;
  • international second-home buyers;
  • long-term tenants;
  • students;
  • senior residents;
  • tourists;
  • hotel guests;
  • corporate occupiers;
  • institutional investors;
  • hotel or residential operators;
  • another developer acquiring a completed or partially completed project.

The strategy should identify:

  • what the customer needs;
  • what the customer can afford;
  • which competing products are available;
  • which features support value;
  • which features add cost without supporting price or demand;
  • how quickly the market can absorb the project;
  • whether the customer is expected to buy, lease, stay or operate;
  • whether the target demand is local, national or international.

The customer definition affects the site, product, design, unit mix, specification, marketing, contract structure and exit route.

043. Select locations using rules, not preference

The location strategy should establish objective selection criteria.

These may include:

  • permitted or potentially compatible uses;
  • planning stability;
  • access and infrastructure;
  • population and employment;
  • tourism or business demand;
  • competing supply;
  • land availability;
  • construction and logistics costs;
  • municipal requirements;
  • environmental and heritage constraints;
  • utilities;
  • seasonality;
  • expected sales or leasing period;
  • operator demand;
  • liquidity at exit.

A location should not be selected only because the developer knows it, likes it or has received an apparently attractive opportunity there.

The applicable territorial plans and restrictions must be reviewed for each site. The official SNIT geoportal, municipal planning portals and published territorial instruments can support initial screening, but a map view alone is not a legal or planning confirmation.

Location brief

For each target area, record:

  • preferred municipalities or submarkets;
  • accepted project types;
  • minimum demand conditions;
  • maximum acceptable planning risk;
  • infrastructure requirements;
  • price and cost evidence required;
  • intended customer;
  • likely exit;
  • conditions that would exclude the location.

054. Choose the development model

A development can be originated and controlled in different ways.

The strategy may involve:

  • direct acquisition of land;
  • acquisition of an existing building;
  • acquisition of a project with planning history;
  • acquisition of shares in a property-owning company;
  • an option to acquire;
  • an exclusivity agreement;
  • a conditional promissory purchase and sale agreement;
  • a joint venture with the landowner;
  • a development-management agreement;
  • phased acquisition;
  • a purchase subject to defined conditions.

The preferred model should reflect:

  • the stage of the project;
  • the certainty of the planning position;
  • the amount of capital available;
  • the seller’s requirements;
  • the need for control;
  • the allocation of planning and title risk;
  • tax consequences;
  • financing requirements;
  • the intended exit.

A share acquisition may preserve contracts, project history or other arrangements held by the target company. It may also transfer corporate, contractual, tax, employment, litigation and other historical liabilities. The choice between an asset acquisition, share acquisition or joint-venture structure should therefore be made after legal, tax and financial assessment, not because one route appears faster.

065. Define the exit before acquisition

The exit strategy determines how the project is expected to generate value.

Possible routes include:

  • sale of individual units;
  • sale of serviced plots;
  • sale of the completed asset;
  • sale of the project company;
  • pre-sales or off-plan sales;
  • leasing and stabilisation;
  • hotel or tourism operation;
  • appointment of an operator;
  • refinancing;
  • phased disposal;
  • retention as a long-term income asset.

The intended exit affects decisions made much earlier. For example:

  • individual unit sales may require horizontal property and a coordinated conveyancing process;
  • a build-to-rent project is assessed on income, operating costs and stabilised value;
  • a hotel requires early consideration of use, typology, operator requirements and the tourism regime;
  • an institutional purchaser may require particular design, sustainability, reporting and warranty standards;
  • the sale of a project company requires a reliable corporate and project data room;
  • refinancing depends on valuation, income, legal completion and lender requirements.

A project should not rely on a single optimistic exit. The strategy should identify a principal exit and at least one realistic alternative.

076. Establish the return requirements

The project should have clearly defined financial decision criteria.

Relevant measures may include:

  • total development cost;
  • gross development value;
  • cost-to-value ratio;
  • profit on cost;
  • project internal rate of return;
  • equity internal rate of return;
  • equity multiple;
  • stabilised yield;
  • break-even sale price;
  • break-even rent;
  • peak equity requirement;
  • interest cover or debt-service measures;
  • residual land value.

Not every measure is appropriate for every project. A short residential development for sale may focus on profit on cost, cash flow and sales absorption. A long-term income asset may place greater weight on stabilised income, operating costs, yield and debt-service capacity.

The strategy should state:

  • the principal return measure;
  • minimum acceptable return;
  • maximum equity commitment;
  • maximum land exposure;
  • target financing level;
  • maximum acceptable project duration;
  • downside conditions that make the project unacceptable.

These are internal investment criteria, not guarantees of performance.

087. Define the capital strategy

The developer should identify how the project is expected to be funded through each phase.

Possible sources may include:

  • sponsor equity;
  • shareholder loans;
  • co-investor equity;
  • landowner participation;
  • senior development finance;
  • bridge finance;
  • mezzanine or subordinated finance;
  • preferred equity;
  • pre-sale receipts, where legally and contractually available;
  • operating cash flow;
  • refinancing.

The strategy should not assume that all funding is available from acquisition. Different sources may become available only after:

  • acquisition;
  • planning progress;
  • satisfaction of lender conditions;
  • a required equity contribution;
  • contractor appointment;
  • pre-sales;
  • independent monitoring;
  • execution of security documents.

The capital strategy should consider:

  • when equity is required;
  • when debt can be drawn;
  • interest and financing fees;
  • lender security;
  • guarantees;
  • cost-overrun obligations;
  • cash-flow gaps;
  • contingency;
  • decision-making rights;
  • investor reporting;
  • restrictions on distributions;
  • refinancing or exit conditions.

The funding structure should be tested against delay and cost increases, not only the base programme.

098. Set the risk limits

Every development involves risk. Strategy determines which risks are acceptable and how much evidence is required before the project proceeds.

Planning risk

  • intended use not permitted;
  • assumed area not supported;
  • dependence on a PDM amendment or reclassification;
  • need for external opinions;
  • protected or constrained land;
  • infrastructure insufficiency;
  • uncertain procedure;
  • expired or incomplete project rights.
+Show details(6)

Legal risk

  • ownership or title inconsistencies;
  • boundary disputes;
  • leases or occupation;
  • easements and charges;
  • unresolved litigation;
  • contractual commitments;
  • corporate liabilities;
  • unclear transferability of project documents or agreements.

Technical risk

  • poor ground conditions;
  • contamination;
  • demolition;
  • retaining structures;
  • complex topography;
  • utilities;
  • access;
  • heritage or archaeology;
  • design coordination.

Commercial risk

  • incorrect target customer;
  • weak absorption;
  • excessive specification;
  • dependence on a narrow buyer group;
  • seasonality;
  • operator availability;
  • falling prices or rents.

Construction risk

  • incomplete design;
  • contractor capacity;
  • price volatility;
  • programme delay;
  • variations;
  • insolvency;
  • quality and defects.

Finance risk

  • insufficient equity;
  • delayed drawdowns;
  • covenant breach;
  • cost overruns;
  • interest-rate exposure;
  • refinancing dependence.

Risk policy

For each material risk, define:

  • whether it is accepted;
  • how it will be investigated;
  • who is responsible;
  • what evidence is required;
  • whether it affects price;
  • whether it must be addressed before acquisition;
  • whether it requires a contractual condition;
  • what event causes withdrawal.

1110. Decide how the project will be governed

Strategy should identify who has authority to make decisions.

This is particularly important where the project involves:

  • multiple shareholders;
  • external investors;
  • a landowner joint venture;
  • lender approval rights;
  • a development manager;
  • an operator;
  • different entities within the ownership structure.

The governance framework should address:

  • who approves an acquisition;
  • who approves the feasibility model;
  • who appoints advisers;
  • who approves design changes;
  • who approves funding;
  • who controls the bank account;
  • who approves the construction contract;
  • who approves cost overruns;
  • which matters require unanimous or investor consent;
  • how conflicts are managed;
  • how deadlock is resolved;
  • who can approve a sale or refinancing;
  • reporting frequency and format.

Governance should be documented in the appropriate corporate and contractual instruments. An informal understanding between investors is not an adequate substitute.

12What should happen during the first 30 days?

Week 1 — Investment brief

Agree:

  • project type;
  • target customer;
  • location criteria;
  • scale;
  • capital;
  • return;
  • risk limits;
  • exit.
+Show details(3)

Week 2 — Market and planning screen

Review:

  • target locations;
  • demand evidence;
  • competing supply;
  • territorial plans;
  • obvious constraints;
  • likely project types;
  • indicative delivery considerations.

Week 3 — Structure and delivery workshop

Consider:

  • acquisition routes;
  • project vehicle;
  • investor roles;
  • financing assumptions;
  • professional team;
  • decision-making;
  • likely programme.

Week 4 — Approval of the strategy

Produce and approve:

  • project brief;
  • site-selection scorecard;
  • investment criteria;
  • initial risk register;
  • preliminary capital plan;
  • adviser brief;
  • opportunity-screening process.

13Documents for this phase

The strategy phase should create:

Investment and development brief

A concise statement of:

  • product;
  • customer;
  • location;
  • scale;
  • capital;
  • return;
  • risk;
  • programme;
  • exit.
+Show details(5)

Site-selection scorecard

A consistent method for comparing:

  • planning;
  • access;
  • infrastructure;
  • market;
  • physical conditions;
  • cost;
  • time;
  • liquidity.

Initial financial framework

A template identifying:

  • land;
  • acquisition costs;
  • construction;
  • professional fees;
  • municipal costs;
  • finance;
  • contingency;
  • revenue;
  • exit costs.

Initial risk register

For each risk:

  • description;
  • probability;
  • impact;
  • evidence required;
  • owner;
  • mitigation;
  • decision deadline.

Decision and governance matrix

A record of:

  • decision-makers;
  • reserved matters;
  • approval thresholds;
  • reporting;
  • escalation.

Adviser brief

A clear description of the project so that legal, planning, design, tax, finance and market advisers investigate the same assumptions.

14The one-page project brief

Before assessing individual opportunities, complete the following:

  • Project type — what are we developing?
  • Customer — who will buy, lease, stay in or operate it?
  • Location — which municipalities or submarkets qualify?
  • Scale — what site area, building area or unit count is appropriate?
  • Product — what unit mix, specification and amenities are required?
  • Capital — how much equity can be committed and when?
  • Return — what is the principal measure and minimum acceptable result?
  • Risk — which risks are acceptable and which cause rejection?
  • Acquisition — direct purchase, project acquisition, company acquisition, option or joint venture?
  • Planning — what minimum level of planning evidence is required before acquisition?
  • Programme — what is the maximum acceptable delivery period?
  • Exit — sale, lease, operation, refinancing or project disposal?

Decision gate

The strategy phase is complete when the developer can answer:

  • What are we building?
  • Who is it for?
  • Where will we consider developing it?
  • What evidence must a site satisfy?
  • How much capital can we commit?
  • What return do we require?
  • What risks will we accept?
  • What risks will make us withdraw?
  • How will the project be acquired and funded?
  • How will value ultimately be realised?

If these questions cannot be answered, the project is not ready for site selection.

Risks at this phase

  • Selecting a site before agreeing the product.
  • Allowing the land opportunity to define the strategy.
  • Using asking prices as evidence of value.
  • Assuming planning capacity without verification.
  • Treating gross building area as saleable or lettable area.
  • Ignoring infrastructure and abnormal costs.
  • Relying on one optimistic revenue case.
  • Choosing the project company for tax reasons alone.
  • Assuming debt will be available on the required terms.
  • Failing to define investor authority and reserved matters.
  • Having no alternative exit.
  • Appointing advisers without a consistent project brief.

Indicative timing and costs

A focused strategy phase commonly takes approximately two to six weeks.

The timing will depend on:

  1. number of investors;
  2. project complexity;
  3. availability of market information;
  4. number of locations;
  5. financing strategy;
  6. need for preliminary legal, planning, tax or technical input.

There is no statutory fee or standard strategy cost. Initial expenditure may include market research, planning advice, legal structuring advice, tax advice, financial modelling, concept design, technical input and project-management support. The developer should define an initial investigation budget and approval limit before detailed work begins.

Common mistakes

  1. 1Starting with “we have found a site”.
  2. 2Describing the strategy only as “residential” or “hotel”.
  3. 3Failing to define the customer.
  4. 4Choosing locations based on familiarity rather than evidence.
  5. 5Confusing permitted use with commercial terminology.
  6. 6Defining the project only by gross building area.
  7. 7Failing to model parking, common areas and technical areas.
  8. 8Using one fixed construction cost for every location and product.
  9. 9Assuming tax efficiency equals project efficiency.
  10. 10Forming an SPV before considering acquisition, funding and exit.
  11. 11Having no clear authority to approve costs or changes.
  12. 12Treating the exit as something to decide after construction.

Strategy checklist

Before moving to Site Screening, confirm that you have:

Progress: 0/18

Progress is saved in this browser only.

Frequently asked questions

Do I need a specific site before preparing a strategy?

No. The strategy should normally be prepared first so that individual sites can be assessed consistently. It can be refined when a real opportunity is identified.

Should I create a Portuguese company immediately?

Not automatically. The acquiring and development structure should be considered against legal, tax, funding, governance and exit requirements before an entity is selected or used.

Can one strategy cover several project types?

It can, but each project type should have its own customer, planning, cost, funding and exit assumptions. A strategy that is too broad may not provide a useful basis for rejecting unsuitable opportunities.

Can I rely on online PDM maps when selecting locations?

They are useful for initial screening but should not be treated as a complete planning confirmation. The applicable plans, written regulations, restrictions and site-specific circumstances must be reviewed.

Should a hotel operator be involved during strategy?

Where the project depends on an operator, brand, management agreement or particular operating model, early operator input can materially affect design, amenities, room mix, technical requirements, costs and financeability.

Is the highest financial return always the best strategy?

Not necessarily. The expected return must be considered against the probability of delivery, capital exposure, duration, liquidity and downside risk.

How detailed should the initial financial model be?

Detailed enough to test the main drivers and expose missing information. It should not create false precision before area, planning, cost, programme and revenue assumptions have been verified.

Tools for this phase

Personal Development Plan

Turn the project brief into a structured list of decisions, documents and next steps.

Build my development plan

Compare Development Locations

Compare target regions by project fit, planning pressure, infrastructure, demand and delivery considerations.

Compare locations

Development Feasibility Check

Test the first area, cost, programme and revenue assumptions.

Start a feasibility check

Next phase

02 — Site Screening

Identify whether a specific site has a credible legal, planning, physical and commercial basis for further investigation.

Continue to Site Screening

Legal support through VVA

VVA can assist with the legal, planning and transaction questions that should be identified before a site or project is acquired.

Legal services are provided by Valente Veiga & Associados.

Official sources

  • Regime Jurídico da Urbanização e da Edificação — Decreto-Lei n.º 555/99, in its current consolidated version.
  • Regime Jurídico dos Instrumentos de Gestão Territorial — Decreto-Lei n.º 80/2015, in its current consolidated version.
  • Direção-Geral do Território — SNIT territorial-plan information.
  • Instituto dos Registos e do Notariado — Portuguese land-registry information.
  • Turismo de Portugal — installation and registration of tourist developments.

Last reviewed: 21 August 2026