Develop in Portugal
FAQ
Phase 08 of 08

Sales, Operation & Exit

Convert the completed development into sales proceeds, operating income or an investment exit.

08Sales, Operation & Exit

At a glance

Indicative duration
6–24 months, often overlapping construction
The decision
How will the completed development be sold, leased, operated, refinanced or disposed of, and on what terms?
Documents
  • Use licence, energy certificate and technical file.
  • Horizontal property deed where units are separated.
  • Sales contracts and, for off-plan, the bank guarantees agreed.

The decision this phase helps you make

How will the completed development be sold, leased, operated, refinanced or disposed of, and on what terms?

At the end of this phase, you should be able to determine:

  • whether the development will be sold, leased, operated, refinanced or retained;
  • whether disposal will occur unit by unit, in bulk or through a sale of the project company;
  • when marketing and pre-sales may begin;
  • which information can legally and accurately be communicated to the market;
  • which sales agents or distribution channels will be used;
  • how reservations and buyer payments will be handled;
  • which terms will govern the contract-promises;
  • how the property-horizontal structure will be completed;
  • which conditions must be satisfied before each final sale;
  • how lender security will be released;
  • how buyers will inspect and receive their units;
  • how defects and consumer claims will be managed;
  • how the completed building will be leased or operated;
  • when the asset will be capable of refinancing;
  • and how investors will receive and realise their returns.

The selected route should be legally deliverable, operationally workable and consistent with the project's financial model.

01Choose the commercial route

A completed development can produce value through several routes.

Unit-by-unit sales

Residential, commercial or mixed-use developments may be divided into autonomous units and sold separately.

This strategy can produce a higher aggregate selling value but may also require:

  • a longer sales period;
  • individual buyer contracts;
  • property-horizontal registration;
  • individual lender releases;
  • repeated completion procedures;
  • condominium arrangements;
  • buyer aftercare;
  • and continuing developer responsibility for unsold units.
+Show details(7)

Bulk property sale

The entire property or a defined part of the development may be sold to one investor.

A bulk sale can simplify completion and accelerate the return of capital, but the buyer may expect:

  • a pricing discount;
  • extensive due diligence;
  • representations and warranties;
  • rent or income support;
  • completion conditions;
  • and protection against development, construction or operational risks.

Sale of the project company

Instead of selling the property directly, the investors may sell the shares or quotas in the company that owns the project.

The company continues to own the property, contracts, licences, liabilities and operational history. A share sale therefore requires due diligence covering the complete company, not only the real estate.

Hold and lease

The project company may retain the property and lease it to residential or commercial occupiers.

This route requires:

  • an appropriate leasing strategy;
  • compliant lease documentation;
  • tenant due diligence;
  • building management;
  • operating budgets;
  • service-charge arrangements;
  • maintenance;
  • insurance;
  • and long-term asset management.

Owner-operated asset

Hotels, serviced accommodation, healthcare, student housing, senior living, flexible offices and other operational assets may be operated by the owner or an affiliated company.

The project return then depends on business performance as well as property value.

Third-party operation

The owner may appoint a specialist operator under a:

  • lease;
  • management agreement;
  • franchise;
  • concession;
  • service agreement;
  • or another operating structure.

The commercial and legal effect of each model is different.

Refinancing and retention

A stabilised asset may be refinanced and retained. Refinancing can repay development debt and return part of the invested capital while preserving ownership of the asset.

It is not equivalent to an exit if the investors remain exposed to:

  • operating performance;
  • interest rates;
  • refinancing maturity;
  • capital expenditure;
  • tenant risk;
  • and future market value.

Mixed strategy

A project may combine several routes. For example:

  • some units may be pre-sold;
  • others may be sold after completion;
  • retail space may be leased;
  • and the remaining income-producing asset may be refinanced or sold.

The legal structure, property-horizontal title, lender documentation and tax model must support the selected combination.

02Define the sales strategy before launch

A sales strategy should identify:

  • target buyers;
  • unit mix;
  • release phases;
  • pricing;
  • permitted discounts;
  • reservation process;
  • deposit structure;
  • contract timetable;
  • buyer-finance assumptions;
  • marketing channels;
  • agent commissions;
  • international distribution;
  • sales targets;
  • lender release prices;
  • completion timetable;
  • and unsold-stock strategy.

Reconcile the strategy with the project

The strategy should reconcile with:

  • the approved project;
  • area schedule;
  • property-horizontal structure;
  • construction programme;
  • financial model;
  • lender covenants;
  • and tax position.

A sales forecast is not only a marketing document. It determines cash flow, debt repayment and the timing of investor returns.

03Build the sales inventory

Create a controlled schedule for every saleable or lettable unit, identifying:

  • unit reference and intended autonomous-unit number;
  • location, floor and permitted use;
  • internal and external area;
  • balconies, terraces, parking and storage;
  • private-use areas and common areas;
  • ownership percentage or permillage;
  • specification, list price and approved discount;
  • reservation and contract status;
  • buyer details, amounts received and outstanding price;
  • lender release amount;
  • anticipated completion, deed date and handover date;
  • and defect status.

Use one area methodology

The same unit should not be described using inconsistent measurements.

Define whether each figure represents:

  • gross construction area;
  • private gross area;
  • dependent gross area;
  • internal usable area;
  • saleable area;
  • external area;
  • or another defined measurement.

The marketing plan, reservation, contract-promise, property-horizontal title, tax records and final sale documents may not use identical concepts. Every document should make clear which area basis it uses.

Control unit changes

If units are combined, divided, renumbered or redesigned after marketing begins, assess the effect on:

  • planning;
  • property horizontal;
  • lender approval;
  • buyer contracts;
  • prices and deposits;
  • areas and common parts;
  • construction;
  • tax;
  • and registration.

A commercial change may require more than an updated price list.

04Appoint the sales team

The developer may use an internal sales team, one exclusive agency, several non-exclusive agencies, international introducers, digital platforms, auction providers or a combination of channels.

Real estate mediation

Portuguese real estate mediation is regulated. An established Portuguese mediator generally requires the applicable IMPIC licence, commonly identified by its AMI number. The mediation agreement must be in writing and address the property, intended transaction, remuneration, insurance and any exclusivity arrangements.

The law also requires mediators to provide accurate and clear information about the property and transaction and establishes rules for amounts received from prospective purchasers before a sale or contract-promise.

Before appointment, confirm:

  • licence or permitted cross-border status;
  • professional insurance;
  • territorial coverage and buyer network;
  • exclusivity, commission and VAT;
  • commission trigger;
  • responsibility for sub-agents;
  • authority to issue marketing materials and permitted representations;
  • reservation process and treatment of buyer payments;
  • data ownership and data protection;
  • anti-money-laundering responsibilities and reporting;
  • termination and post-termination commission rights.

Commission trigger

Commission may become payable at the final sale or, if the mediation agreement expressly provides, when the contract-promise is signed. The agreement should not leave the trigger unclear.

It should also address:

  • buyer withdrawal;
  • developer default;
  • buyer introduced before termination;
  • direct sales;
  • duplicate introductions;
  • assignment of a buyer's contractual position;
  • unit substitutions;
  • and sales completed through another agent.

Sales authority

Agents should not be authorised informally to:

  • change prices;
  • promise discounts;
  • agree variations;
  • receive unrestricted funds;
  • commit to completion dates;
  • alter specifications;
  • guarantee views or returns;
  • or make planning or tax representations.

Use a written authority matrix.

05Prepare accurate marketing materials

Marketing information must be consistent with the project that can actually be delivered. Review the website, brochures, price lists, plans, area schedules, computer-generated images, model units, specifications, virtual tours, advertising, social-media content, sales presentations and agent scripts.

Clearly distinguish fact from illustration

Computer-generated images and artistic impressions should not be presented as exact representations of the completed project.

Identify where images include:

  • indicative furniture;
  • landscaping at maturity;
  • views from an approximate position;
  • decorative items not included in the price;
  • optional upgrades;
  • unapproved future phases;
  • or surrounding developments outside the developer's control.

A general disclaimer will not necessarily correct a specific misleading statement.

+Show details(4)

Do not market unapproved characteristics as certain

Avoid presenting as final:

  • unit layouts that remain subject to approval;
  • a use that has not been confirmed;
  • a tourist classification not yet obtained;
  • common facilities dependent on a later phase;
  • areas that have not been verified;
  • or completion dates that the programme cannot support.

Public statements may affect conformity

For residential property sold by a professional to a consumer, public statements about the property's characteristics can be relevant when determining whether the property conforms to the sale contract.

Marketing, samples and model units must therefore be coordinated with the contractual specification and completed works, under the consumer conformity regime for residential property (Decree-Law 84/2021).

Energy certification

Where the energy-certification regime applies:

  • the energy class must be included in transaction advertising;
  • the relevant certificate information must be supplied before the contract-promise;
  • and the certificate must be available for the final transaction.

The obligations extend to property owners, mediators and advertising platforms in the circumstances defined by Decree-Law 101-D/2020.

Loteamento information

Where the units are built on land subject to a loteamento operation, confirm the statutory information that must appear in advertising and transaction documents. The applicable planning title, date and validity should be checked before the campaign launches.

06Reservations

A reservation normally gives the prospective buyer a limited period in which to progress towards a contract-promise. It should not be treated as a transfer of ownership.

The reservation document should address:

  • parties and unit;
  • reservation period and amount;
  • price and payment method;
  • whether the amount is refundable and refund events;
  • expiry;
  • KYC requirements and documentation to be provided;
  • whether the developer may continue marketing;
  • whether the reservation is conditional;
  • treatment of the amount when the CPCV is signed;
  • and confirmation that ownership will transfer only through the legally required transaction.

Reservation payments

State who receives the payment:

  • developer;
  • lawyer's client account;
  • escrow provider;
  • mediator;
  • or another authorised recipient.

Do not use the word "escrow" unless the funds are genuinely subject to a documented escrow arrangement. Where a real estate mediator receives money before completion or the contract-promise, statutory custody and repayment rules may apply.

Reservation expiry

Define what happens if:

  • the buyer does not provide KYC information;
  • the buyer's lawyer does not respond;
  • the CPCV remains unsigned;
  • finance is refused;
  • the developer changes the unit;
  • or either party decides not to proceed.

An indefinite reservation can obstruct the sales programme without creating a bankable contract.

07Buyer due diligence and anti-money-laundering controls

Real estate development, purchase, sale, resale, leasing and mediation fall within the real estate activities identified by Portuguese anti-money-laundering legislation (Law 83/2017). Relevant obliged entities must implement identification, due-diligence, record-keeping, examination, reporting and other preventive measures.

The sales process should collect and verify, as applicable:

  • buyer identity, tax identification and address;
  • marital status and representatives;
  • powers of attorney;
  • corporate documents and management authority;
  • ownership structure and beneficial owners;
  • source of funds and payment account;
  • politically exposed person status;
  • sanctions exposure;
  • and purpose of the acquisition.

Coordinate the parties

The developer should define which checks are performed by the developer, mediator, lawyer, bank, notary or transaction platform.

Reliance on another participant does not automatically eliminate the developer's own legal obligations.

Payment controls

Project procedures should prohibit:

  • unexplained third-party payments;
  • payments from accounts unrelated to the buyer;
  • splitting of transactions to avoid controls;
  • undocumented cash;
  • overpayments followed by repayment to another account;
  • and refunds to a different person or account without verification.

KYC should begin before material funds are accepted, not on the day of the final deed.

08The contract-promise — CPCV

A Portuguese contract-promise of purchase and sale is commonly known as a CPCV. It creates contractual obligations to enter the final transaction but does not normally transfer ownership itself.

Portuguese Civil Code rules concerning form, deposits or "sinal", default, specific performance, real effect and registration may apply depending on the transaction and drafting.

The document should be prepared or reviewed for the particular project. Off-plan, completed, residential, commercial, tourist and investor transactions may require different provisions.

Parties and authority

Confirm seller, buyer, legal representatives, signing powers, beneficial owners, marital information, tax identification and any permitted nominee or assignee.

+Show details(10)

Property identification

Identify:

  • land-registry description and tax registration;
  • building, unit and floor;
  • plans;
  • parking, storage and terraces;
  • exclusive-use areas and common facilities;
  • and the intended autonomous fraction.

If the property-horizontal title has not yet been registered, explain how the future unit will be identified.

Planning and construction status

State accurately the planning procedure, construction status, expected completion, permitted use, outstanding approvals, infrastructure status and any conditions that must be satisfied before the final sale.

Do not imply that a reservation or CPCV confirms planning legality.

Price and payments

Define:

  • total price and VAT treatment where relevant;
  • reservation credit and deposit;
  • staged payments and payment dates;
  • payment accounts and documentary evidence;
  • interest on late payment;
  • final balance and permitted deductions.

Amounts delivered under the CPCV may constitute a "sinal" with statutory consequences, depending on the wording and circumstances. The parties should understand the consequences of loss of the deposit, repayment in double, specific performance, other remedies and any contractually agreed limitations.

Conditions precedent

Possible conditions include satisfactory title, property-horizontal registration, planning or use status, construction completion, infrastructure completion, lender release, mortgage cancellation, approval of a design amendment, buyer KYC, buyer finance or delivery of defined documents. For each, identify:

  • who controls the condition;
  • evidence required;
  • deadline;
  • extension rights;
  • waiver rights;
  • and consequences if it is not satisfied.

Completion date

Distinguish between:

  • target completion;
  • anticipated readiness;
  • contractual completion window;
  • longstop date;
  • force-majeure extension;
  • buyer-notice period;
  • and the date of the final transaction.

A construction programme is not automatically an unconditional contractual promise.

Design, specification and area changes

The CPCV should define which plans and specification apply, permissible substitutions, equivalent materials, authority-required changes, technical changes, buyer-requested variations, area tolerances, material-change thresholds, price adjustments, buyer termination rights and the document hierarchy. On areas, state:

  • the contractual area definition;
  • source of measurement;
  • treatment of balconies and terraces;
  • permitted tolerance;
  • remedy for material difference;
  • and whether the purchase price changes.

A clause allowing any change at the developer's discretion may create enforceability and consumer-law risk, and an area tolerance should not be used to conceal a predictable or already known difference.

Assignment and resale

Define whether the buyer may assign the CPCV, nominate another purchaser, sell the contractual position, add or remove a co-purchaser or transfer to a connected company. Consider:

  • developer consent;
  • KYC;
  • lender requirements;
  • commission and tax;
  • administrative fee;
  • and continuing liability of the original buyer.

Buyer finance

If the transaction is conditional on buyer financing, define required evidence, application deadline, lender refusal, maximum or minimum loan, valuation shortfall and refund consequences.

If it is not finance-conditional, the buyer should understand that inability to obtain finance may not excuse completion.

Default and remedies

Address seller default, buyer default, failure to attend completion, failure to deliver documents, late payment, notice to remedy, termination, deposit consequences, specific performance, interest and recovery of costs.

The remedies must be coordinated with mandatory law and any consumer protections.

Language and interpretation

For international buyers, determine the governing version, translation, interpreter requirements, notices, governing law, courts or arbitration and service of proceedings.

A translation should not be allowed to create different commercial obligations.

09Off-plan buyer protection

A buyer signing a CPCV for a unit that remains under construction is exposed to:

  • planning risk;
  • construction delay;
  • developer insolvency;
  • lender enforcement;
  • specification changes;
  • area changes;
  • failure to create the autonomous fraction;
  • and failure to obtain the required completion or use status.

Do not assume statutory escrow

Buyer payments are not automatically protected merely because the project is a new development.

Depending on the transaction, protection may be created through:

  • escrow;
  • bank guarantee;
  • parent-company guarantee;
  • deposit insurance;
  • registered contractual rights;
  • real effect and registration of the promise;
  • restricted project accounts;
  • lender acknowledgements;
  • or staged payments tied to verified milestones.

The availability, legal effect, priority and cost of each mechanism must be confirmed.

Lender security

If the property is mortgaged, the buyer contract should address how the unit will be released at completion. The process may require:

  • minimum release price;
  • lender consent;
  • allocation of sale proceeds;
  • partial mortgage cancellation;
  • registration documents;
  • and coordination between buyer funds, lender repayment and title transfer.

A promise by the developer to release a mortgage is not the same as a binding lender commitment.

10Sales under development finance

The lender may control permitted unit prices, minimum release prices, discounts, the form of CPCV, deposit accounts, buyer incentives, sales milestones, use of deposits, completion conditions and application of sale proceeds.

Release price

The release price is the amount the lender requires before releasing security over a unit. It may not be the same as:

  • sale price;
  • outstanding debt allocated to the unit;
  • construction cost;
  • or net proceeds.

Sales proceeds

The finance documents may require proceeds to be applied to:

  • transaction taxes and mandatory deductions;
  • completion costs;
  • lender fees and interest;
  • debt repayment;
  • reserve accounts;
  • approved project costs;
  • shareholder debt;
  • investor distributions.

The actual order depends on the finance documents and company law.

Reconcile sales reporting

Maintain one controlled record of available units, reserved units, exchanged CPCVs, completed sales, cancellations, gross prices, discounts, incentives, deposits, receivables, commissions, taxes, lender releases and net cash.

Sales reports, accounting records and lender reports should reconcile.

11Property horizontal

A multi-unit building will commonly need to be constituted in propriedade horizontal before its autonomous units can be transferred separately.

Under the Portuguese Civil Code, units intended for separate ownership must be independent and distinct and have their own exit to a common part or the public way. The constitutive title identifies the autonomous units and their relative values, and the Civil Code also regulates common parts and condominium relationships.

Define the autonomous units

The property-horizontal documentation should coordinate unit numbering, permitted use, floor, area, parking, storage, balconies, terraces, gardens, roof areas, technical spaces and ownership percentages.

+Show details(4)

Ownership versus exclusive use

A space may be:

  • part of an autonomous unit;
  • a common part;
  • a common part allocated to the exclusive use of one unit;
  • or subject to another legal arrangement.

Marketing should not describe exclusive use as ownership unless that is legally correct.

Condominium regulations

The title or separate regulations may address use of common areas, permitted activities, noise, pets, signage, alterations, short-term accommodation, parking, security, waste, maintenance, insurance, service contracts and cost allocation.

Restrictions must be legally valid and consistent with the intended use and title.

Initial condominium budget

Prepare a realistic budget covering cleaning, lifts, security, electricity, water, landscaping, pools, fire systems, maintenance, insurance, management, reserve requirements and major equipment.

Artificially low service-charge estimates can create disputes after handover.

Developer-controlled period

While units remain unsold, define:

  • developer voting rights;
  • contributions for unsold units;
  • appointment of the administrator;
  • handover of documents;
  • transfer of service contracts;
  • treatment of defects;
  • and transition to owner control.

The developer should not use the condominium structure to shift its own construction or warranty liabilities to purchasers.

12Tourist developments in property plural

Tourist developments containing separately owned units are subject to a specific legal framework in addition to general property-horizontal rules.

The Portuguese tourist-development regime establishes, among other matters, a constitutive title for developments in plural ownership, continuing tourist use, management and operating arrangements, owner contributions and the rights and obligations of unit owners.

Each tourist development is generally operated by a single operating entity responsible for its overall functioning and service level. Where ownership and operation are separated, the operator requires a legal right to operate the accommodation units. The development and its valid opening title are recorded through the National Register of Tourist Developments (RNET).

A tourist unit should not be marketed as equivalent to an ordinary unrestricted residential apartment without analysing:

  • permitted use;
  • compulsory tourist operation;
  • owner-occupation rights;
  • rental arrangements;
  • operator term and fees;
  • furniture requirements;
  • revenue sharing;
  • transfer restrictions;
  • and the constitutive title.

13Prepare for the final sale

Before scheduling the final transaction, confirm that the seller can deliver the contractual and legal position.

Seller authority

Confirm company existence, ownership, beneficial ownership, management authority, corporate approval, signing powers, powers of attorney and lender consent.

+Show details(4)

Property documentation

The completion file may include:

  • current land-registry certificate;
  • tax record;
  • cadastral or boundary information;
  • property-horizontal title and unit description;
  • planning title;
  • completion or use documentation;
  • energy certificate;
  • technical building documentation;
  • condominium documents;
  • infrastructure evidence;
  • lender release;
  • and evidence concerning encumbrances.

The exact documents depend on the property, date, municipality, planning history and transaction route.

Buyer documentation

Confirm identity, Portuguese tax number, marital information, representation, corporate authority, beneficial ownership, KYC clearance, payment source, tax assessment and financing documents.

Tax and completion statement

Prepare a statement showing price, amounts already paid, final balance, interest, agreed credits, upgrades, taxes, commissions, lender repayment, retention and the net amount payable to the seller.

Public deed or authenticated document

The final transfer may be completed through the legally permitted form, including the applicable registration procedure. Portugal's Casa Pronta service can coordinate property contracts, mortgages, property-horizontal acts and registration in a single service.

The chosen route should be agreed early enough to coordinate parties, documents, payments, bank representatives, mortgage cancellation, registration and interpreter requirements.

14Current urban-title position at property transfer

Decree-Law 10/2024 removed the general requirement to exhibit or prove the existence of the use authorisation and housing technical file at the transfer of an urban property. Instead, the professional formalising the transaction must currently warn that the property may not have the urban titles required for construction or use.

This does not mean that:

  • the property is lawful;
  • the intended use is permitted;
  • missing planning documents are irrelevant;
  • the buyer has accepted every planning risk;
  • the lender will fund;
  • or the seller has complied with its contractual disclosures.

Change scheduled for 1 October 2026

Decree-Law 108/2026 introduces a requirement for transaction documents involving urban construction land, buildings and autonomous units to state whether the corresponding urban title has been presented, is declared by the seller to exist but has not been presented, or does not exist. The provision includes a specific consequence for omission from the transaction document.

The principal entry into force of this revised RJUE framework was postponed to 1 October 2026 by Decree-Law 155-B/2026.

Every sale, lease, CPCV and completion procedure scheduled on or after that date should be reassessed against:

  • the legislation then in force;
  • transitional provisions;
  • official forms;
  • registration practice;
  • municipal implementation;
  • and professional guidance.

A transaction should still be preceded by planning and title due diligence.

15Buyer inspection and handover

The final sale and physical handover may occur on the same date or at different times. The contracts should make the sequence clear.

Completion notice

The seller should provide the contractual notice confirming readiness for completion, the proposed transaction date, outstanding balance, required buyer documents, inspection procedure and handover arrangements.

+Show details(4)

Pre-completion inspection

A buyer inspection may identify incomplete or defective items. Use a written inspection record containing unit, date, attendees, item, location, photograph, responsibility, target completion and status, distinguishing between:

  • a minor defect that does not prevent completion;
  • an incomplete contractual obligation;
  • a safety or habitability issue;
  • and a dispute concerning the specification.

Keys, access and handover information

Record delivery of keys, access cards, remote controls, parking devices, alarm codes, mailbox keys and digital-access credentials, and provide as applicable:

  • appliance manuals and equipment warranties;
  • maintenance instructions and finish schedules;
  • emergency contacts and utility information;
  • energy certificate;
  • condominium contacts and house rules;
  • defect-reporting procedure;
  • and restrictions affecting alterations.

Utilities and meters

Confirm meter references, readings, transfer process, temporary supplies, common supplies and responsibility for charges before and after handover.

Handover of common areas

The common parts should be transferred to the condominium or building-management structure through a documented process. The file may include:

  • as-built drawings;
  • equipment schedules;
  • maintenance contracts;
  • inspection records;
  • warranties;
  • statutory certificates;
  • access credentials;
  • operating manuals;
  • and outstanding-defect lists.

16Consumer protection and residential property conformity

Decree-Law 84/2021 applies a specific conformity regime to residential urban property sold by a professional to a consumer. The professional must deliver property that conforms to the contract and has the expected qualities concerning quality, safety, habitability, environmental protection and functionality. The law also considers descriptions, samples, models and public statements concerning the property.

The professional is generally responsible for qualifying nonconformities that become apparent within ten years for structural construction elements and five years for other nonconformities. Available consumer rights may include repair, replacement, proportionate price reduction or termination, subject to the conditions and limitations of the legislation.

This seller-to-consumer regime is separate from:

  • the contractor's obligations to the developer;
  • consultant liability;
  • construction-contract warranty periods;
  • insurance;
  • and contractual guarantees.

The developer should ensure that its rights against the contractor and design team remain capable of supporting its obligations to buyers.

17Establish the aftercare system

Buyer aftercare should be designed before the first unit is handed over.

Reporting channel and triage

Provide one controlled channel for defect reports, photographs, access arrangements, urgent issues and status updates, and classify reports as:

  • emergency;
  • health or safety;
  • water ingress;
  • major systems failure;
  • ordinary defect;
  • maintenance issue;
  • user damage;
  • or non-defect query.
+Show details(4)

Responsibility

Determine whether the item concerns the developer, main contractor, subcontractor, consultant, supplier, condominium, utility provider, operator or owner.

The buyer should not be required to coordinate the developer's supply chain.

Access and evidence

Record date notified, inspections, diagnosis, access attempts, remedial work, completion, buyer confirmation and recurrence.

Common defects

Coordinate defects affecting façades, roofs, waterproofing, lifts, fire systems, drainage, mechanical systems, landscaping, garages and other common areas with the condominium or building manager.

Financial provision

The project close-out budget should retain sufficient funding for:

  • aftercare staff;
  • inspections;
  • urgent works;
  • unresolved claims;
  • contractor insolvency;
  • common-area defects;
  • and professional fees.

Releasing all project cash at completion can leave the seller unable to meet continuing obligations.

18Leasing the development

Where the project will be retained, the leasing strategy should be established before completion.

Residential leasing

Consider target tenant, furnished or unfurnished model, lease duration, rent, deposits and guarantees, permitted occupation, utilities, maintenance, pets, subletting, termination, inventory and tenant communications.

+Show details(3)

Commercial leasing

Commercial lease negotiations may address permitted use, lease term, break rights, rent-free period, fit-out, turnover rent, indexation, bank guarantee, service charge, repairs, insurance, signage, assignment, subletting, reinstatement, opening obligations and landlord works.

Planning and use

A lease does not cure an unlawful or unauthorised use.

Confirm that:

  • the unit can lawfully be used for the proposed activity;
  • any fit-out is permitted;
  • building and condominium rules allow the activity;
  • and any sector-specific approvals can be obtained.

Lease documents

Portuguese urban leases are governed by the Civil Code, the NRAU and related legislation. The documentation should be reviewed against the current rules applicable to:

  • residential or non-residential use;
  • duration, renewal and termination;
  • formalities;
  • deposits and guarantees;
  • rent updates;
  • tax reporting;
  • and dispute procedures.

19Select the operating model

Operational developments require a structure that separates property ownership, business operation and brand rights where appropriate.

Owner operation

The owner controls the business and retains the full operating result, but also assumes responsibility for:

  • staff;
  • regulatory compliance;
  • systems and suppliers;
  • licences;
  • guest or resident services;
  • operating losses;
  • and working capital.
+Show details(4)

Operating lease

The operator leases the property and pays fixed, indexed or turnover rent, or a combination. The lease should allocate:

  • maintenance;
  • replacement expenditure;
  • insurance;
  • statutory compliance;
  • licences;
  • brand standards;
  • and return condition.

Management agreement

The operator manages the business for the owner. The owner generally retains the operating risk and funds payroll, operating costs, working capital, furniture and equipment and capital expenditure. The agreement may include:

  • base fee and incentive fee;
  • performance test;
  • budget approval;
  • owner priority;
  • operator system charges;
  • termination rights;
  • and handover obligations.

Franchise

A franchise permits use of a brand, systems and distribution platform while the business is operated by the owner or another operator. The franchise agreement should be coordinated with management, technical services, design approval, opening standards, marketing, reservation systems and brand-mandated capital expenditure.

Operator selection

Assess track record, local capability, financial strength, brand, distribution, operating forecasts, pre-opening team, technical services, proposed fees, owner protections and exit flexibility.

A recognised brand does not eliminate the need to test the operator's financial assumptions.

20Operator agreement issues

The operating documents may address term, renewal, territorial protection, exclusivity, pre-opening and technical services, staffing, key appointments, operating standards, budgets, bank accounts, procurement, related-party charges, central services, intellectual property, data, insurance, reporting, fees, owner priority, performance tests, cure rights, termination, lender step-in, sale of the property and transition to a replacement operator.

Budget control

Define the initial operating budget, annual approval, emergency expenditure, unbudgeted expenditure, capital expenditure, furniture replacement reserve and the consequences of disagreement.

Performance test

A performance test may compare actual results with budget, revenue, gross operating profit, competitor-set performance or another agreed benchmark.

The test should not be capable of being avoided through accounting classifications controlled solely by the operator.

Sale and finance

The agreement should address assignment to a purchaser, lender security, direct agreements, step-in rights, non-disturbance, termination on sale and compensation.

An operator contract that cannot be transferred or terminated may materially reduce the property's sale value.

21Operational readiness

The building should not open merely because the construction team has achieved completion. Prepare an opening plan covering property, physical, people, systems, commercial and financial readiness.

Property and regulatory readiness

  • planning and use position;
  • sector-specific approvals and registrations;
  • fire-safety documentation;
  • accessibility and inspections;
  • environmental-health requirements;
  • signage and complaints procedures;
  • and insurance.
+Show details(3)

Physical readiness

  • furniture, fixtures and equipment;
  • operating supplies and spare parts;
  • testing and commissioning;
  • maintenance systems;
  • cleaning, security and waste;
  • landscaping;
  • and snagging.

People and systems

  • organisational structure, recruitment and training;
  • payroll, uniforms and policies;
  • health and safety and emergency procedures;
  • property-management system and point of sale;
  • reservations and access control;
  • accounting, procurement and CRM;
  • cybersecurity, data protection and reporting.

Commercial and financial readiness

  • branding, photography and website;
  • distribution, pricing and opening offers;
  • contracts, deposits and cancellation policy;
  • customer communications;
  • working capital and pre-opening budget;
  • operating accounts, payment systems and cash controls;
  • insurance, tax registration and approval authorities.

Opening delays and early operating losses should be included in the project financial model.

22Stabilisation

An operational asset is normally considered stabilised when it has achieved a supportable level of recurring performance.

Relevant evidence may include:

  • occupancy and rent collection;
  • average daily rate and revenue per available room;
  • tenant retention;
  • operating margin and net operating income;
  • lease maturity, arrears and concessions;
  • service-charge recovery;
  • and capital-expenditure requirements.

Stabilisation should not be declared solely because one strong month has occurred. The financial model should distinguish between opening, ramp-up, temporary incentives, normalised performance and sustainable stabilised income.

23Refinancing the completed asset

A refinancing may replace development finance with longer-term investment debt. The lender may review title, planning and use, completion documents, construction defects, property horizontal, leases, operator contract, operating history, valuation, income, tenant concentration, capital expenditure, insurance, tax and environmental performance.

Refinancing proceeds

Do not assume that all new debt can be distributed to investors. Refinancing documents, company law, tax, reserves and future capital requirements may restrict distributions.

Debt-service capacity

For income-producing assets, test:

  • interest cover;
  • debt-service cover;
  • vacancy;
  • rent reduction;
  • operating-cost increase;
  • capital expenditure;
  • interest-rate increase;
  • and lower valuation.

A refinancing that depends on optimistic stabilised income may simply postpone the funding problem.

24Prepare the investment exit

A controlled exit process should begin before the asset is placed on the market.

Exit objectives

Define target price, minimum acceptable proceeds, preferred structure, timing, confidentiality, tax result, debt repayment, investor approvals and acceptable continuing liability.

Sale preparation

Resolve or disclose:

  • title defects;
  • planning gaps and incomplete registrations;
  • construction claims and outstanding defects;
  • unpaid contractors;
  • buyer disputes;
  • lease inconsistencies and operator defaults;
  • tax exposures;
  • environmental issues;
  • and corporate-record deficiencies.

Unresolved matters may reduce price, delay closing or require escrow and indemnities.

Appoint advisers

The team may include legal counsel, tax adviser, corporate-finance adviser, real estate agent, technical adviser, valuation adviser, accountant and environmental consultant. The mandates should define scope, exclusivity, fees, success fee, conflicts, confidentiality, data-room access and transaction authority.

25Asset sale versus share sale

Asset sale

The buyer acquires the property or other identified assets. The seller generally retains the company and liabilities not expressly transferred.

The process may require:

  • property-transfer documentation;
  • discharge of security;
  • property registration;
  • assignment or replacement of contracts;
  • tenant or operator coordination;
  • and transfer-tax analysis.

Share sale

The buyer acquires the company that owns the project. The company retains:

  • property;
  • contracts;
  • employees;
  • debt;
  • tax history;
  • disputes;
  • permits;
  • and liabilities.

The buyer will normally request broader corporate, tax and operational protection.

Compare the complete outcome

The two routes should be compared on:

  • price;
  • tax;
  • transaction costs;
  • transferability of contracts;
  • lender consent;
  • regulatory approvals;
  • due diligence;
  • warranties;
  • inherited liabilities;
  • operational continuity;
  • and net investor proceeds.

A share sale is not automatically tax-free or free from property-transfer tax issues. Portuguese IMT rules can apply to certain acquisitions of interests in property-owning entities where statutory conditions are met.

26Build the exit data room

A seller-controlled data room may include:

Corporate and property

  • incorporation documents, articles and ownership;
  • beneficial ownership and corporate approvals;
  • accounts, shareholder arrangements and group contracts;
  • land-registry documents, tax records and plans;
  • surveys, title reports and easements;
  • mortgages, leases and property-horizontal documentation.
+Show details(3)

Planning and construction

  • PIP, licences and communications;
  • approved project, amendments and responsibility statements;
  • municipal correspondence and sector approvals;
  • completion or use documentation;
  • building contract and consultant appointments;
  • programme, payment records and variations;
  • completion certificates, warranties, guarantees and insurance;
  • defects, claims and as-built information.

Sales, leasing and operation

  • sales schedule, reservations, CPCVs and deeds;
  • deposits, commissions and buyer claims;
  • leases, guarantees, arrears and tenant correspondence;
  • operator and franchise agreements;
  • licences, registrations and budgets;
  • management accounts and performance reports;
  • employee information, supplier contracts and capital-expenditure plans.

Finance, tax, disputes and compliance

  • facility agreements, security and guarantees;
  • lender consents, covenant reports, hedging and repayment statements;
  • tax returns, assessments and clearance information;
  • VAT records, transfer-pricing documentation, tax losses and audits;
  • litigation, arbitration, complaints and regulatory matters;
  • AML procedures, data protection, environmental matters and insurance claims.

Information should be complete, current, indexed, internally consistent, appropriately redacted and supported by a disclosure process.

27Exit transaction process

A structured disposal normally follows twelve steps:

  • Step 1 — Confirm the exit route: compare unit sales, bulk property sale, share sale, refinancing and continued operation.
  • Step 2 — Prepare the asset: resolve material title, planning, construction, operational and financial issues.
  • Step 3 — Determine value: obtain appropriate market, investment and tax analysis.
  • Step 4 — Prepare marketing information: teaser, information memorandum, financial information and data room.
  • Step 5 — Approach buyers through a bilateral, limited or competitive process.
  • Step 6 — Receive offers and compare price, structure, proof of funds, finance condition, due-diligence scope, timetable, exclusivity, security and contractual qualifications.
  • Step 7 — Select the preferred buyer and agree heads of terms, identifying which provisions are binding.
  • Step 8 — Complete due diligence: coordinate questions, data-room updates, site access and management presentations.
  • Step 9 — Negotiate the transaction documents: price, adjustments, conditions, warranties, disclosures, indemnities, liability limitations, security, termination and completion.
  • Step 10 — Obtain approvals: investor, board, lender, operator, regulatory and, where relevant, competition or foreign-investment analysis.
  • Step 11 — Complete: coordinate payment, debt discharge, title or share transfer, registration and delivery of control.
  • Step 12 — Manage post-completion obligations: price adjustments, escrow, retentions, warranty claims, tax filings, transition services and final investor distributions.

28Seller warranties and liability

A purchaser may request warranties concerning corporate authority, title, planning, construction, property condition, environmental matters, contracts, employees, tax, accounts, litigation, insurance, data protection and regulatory compliance.

Disclosure

The seller should disclose exceptions accurately and specifically. Uploading a large volume of documents without a controlled disclosure process may not provide the intended contractual protection.

Liability limitations

The transaction documents may address:

  • financial caps;
  • minimum claims and aggregate thresholds;
  • time limits;
  • knowledge qualifications;
  • mitigation;
  • double recovery;
  • insurance recovery;
  • and exclusive remedies.

Security for claims

A buyer may request escrow, price retention, bank guarantee, parent guarantee, holdback or warranty-and-indemnity insurance.

The structure should reflect the seller's intended distribution and winding-up timetable.

29Tax planning for sales and exit

The tax position should be reviewed before setting prices, signing CPCVs, entering leases, refinancing or selecting an asset or share sale. The analysis may include:

  • corporate income tax;
  • VAT;
  • IMT and Stamp Duty;
  • municipal taxes;
  • inventory or investment-property treatment;
  • revenue recognition and deductibility of selling costs;
  • transfer pricing and withholding tax;
  • tax losses;
  • profit distributions and shareholder-loan repayments;
  • liquidation;
  • and investor residence.

VAT

Portuguese VAT treatment of property sales, construction, leasing, options to tax and related expenditure can be complex. Do not assume that:

  • the sale is subject to VAT;
  • the sale is exempt;
  • all input VAT is recoverable;
  • or an option to tax will be available.
+Show details(3)

Buyer taxes

The buyer may be responsible for IMT and Stamp Duty on a direct property acquisition, subject to the property, value, use, buyer and any applicable exemption. The sales team should not provide definitive tax calculations without an approved and current methodology.

Share sale

The seller and buyer should review capital-gains taxation, participation exemptions, withholding, investor jurisdiction, real-estate-rich company rules, transfer pricing and possible IMT consequences.

Net proceeds

The investment return should be calculated after:

  • debt repayment and break costs;
  • tax;
  • commissions and legal fees;
  • retentions and warranty security;
  • project close-out;
  • and remaining liabilities.

Gross sale price is not the investor distribution.

30Sales, operation and exit cost categories

Allow for:

  • market research, branding and marketing;
  • photography and visualisation, model unit, website and technology;
  • sales suite;
  • agency commissions and referral fees;
  • legal documentation and translations;
  • notarial and registration work;
  • property-horizontal documentation and energy certificates;
  • buyer KYC and lender-release costs;
  • taxes and buyer incentives;
  • snagging, aftercare and condominium setup;
  • leasing fees and tenant incentives;
  • operator selection, technical services and franchise fees;
  • pre-opening payroll, working capital, furniture and equipment;
  • refinancing fees and valuation;
  • transaction advisers and data-room preparation;
  • warranty security and closing or liquidation costs.

Identify whether each cost is included in the project budget, paid from sales proceeds, lender-funded, recurring, recoverable or retained after completion.

The sales, operation and exit decision gate

Before marketing, contracting, opening or exiting, confirm the following.

  • Commercial strategy: is the chosen route consistent with the investment model, are target buyers or tenants defined, are release phases and pricing approved, is the unsold-stock strategy realistic and are exit timing and minimum proceeds agreed?
  • Property and planning: is ownership confirmed, is the permitted use suitable, are marketed units consistent with the approved project, is the property-horizontal structure deliverable, are completion and urban-title requirements understood and has the 1 October 2026 legal transition been considered?
  • Marketing: are plans, areas and specifications controlled, are visualisations clearly identified, are claims supportable, is energy information included, is required loteamento information included and are agents using approved materials?
  • Contracts: is the reservation form approved, is the CPCV appropriate for the project, are deposit consequences clear, are change, delay and area provisions legally reviewed, are consumer terms fair and transparent and are lender conditions reflected?
  • Buyer and payment controls: is KYC complete, are beneficial owners identified, is source of funds understood, are permitted payment accounts defined, are refunds controlled and are deposits correctly recorded?
  • Completion: is the unit legally and physically ready, are title and registration documents available, is the lender release arranged, is the completion statement reconciled, is the buyer inspection complete and are keys, manuals and utilities ready?
  • Consumer and aftercare: is there a defect-reporting system, are urgent-response procedures established, are contractor and supplier rights preserved, is funding retained for aftercare and are common-area defects managed?
  • Operation: is the operator appointed, are operating approvals and registrations in place, is the building commissioned, is the pre-opening budget funded, are staff, systems and contracts ready and is the asset insured?
  • Exit: is the data room complete, are unresolved liabilities identified, is lender and investor approval available, has the asset-versus-share structure been tax-reviewed, are warranty liabilities and security understood and have net investor proceeds been calculated?

The project should not launch, open or complete an exit based solely on a commercial deadline if the legal, physical or financial delivery conditions are not satisfied.

Key risks in this phase

  • Marketing information that does not match the approved project, areas or specification.
  • Reservation and deposit arrangements without documented custody, refund and KYC rules.
  • Buyer payments assumed to be protected when no escrow, guarantee or registered right exists.
  • Lender release conditions that prevent completion of signed buyer contracts.
  • Property-horizontal title that does not support the units, parking or exclusive-use areas being sold.
  • Consumer conformity liability lasting up to ten years without matching contractor and consultant remedies.
  • Aftercare and defect costs unfunded because project cash was distributed at completion.
  • Operational assets opened before commissioning, staffing, systems and approvals are complete.
  • Stabilisation declared early, leading to a refinancing that cannot be serviced.
  • Asset-versus-share structures selected on headline tax alone, leaving inherited liabilities unpriced.

Indicative programme

Timing varies by project and exit route. As an initial planning assumption:

  1. sales-strategy preparation: 3–8 weeks;
  2. marketing-material preparation: 4–12 weeks;
  3. agency appointment: 2–6 weeks;
  4. reservation-to-CPCV process: 2–8 weeks per buyer;
  5. property-horizontal preparation and registration: 4–16 weeks or longer;
  6. unit completion and deed preparation: 2–8 weeks;
  7. operational pre-opening: 3–12 months;
  8. leasing and stabilisation: 6–36 months;
  9. refinancing: 8–20 weeks;
  10. bulk asset or share-sale process: 3–9 months;
  11. complex institutional exit: 6–12 months or longer.

Planning, registration, buyer finance, lender release, operator approvals and due diligence can extend these periods materially.

Common sales, operation and exit mistakes

  1. 1Launching before the unit information is controlled — inconsistent plans, areas, prices and specifications create buyer disputes and undermine lender reporting.
  2. 2Marketing an unapproved use — a brochure cannot create planning rights.
  3. 3Treating computer-generated images as harmless — specific visual representations may influence contractual expectations.
  4. 4Using an unlicensed or incorrectly appointed intermediary, creating regulatory, contractual and commission disputes.
  5. 5Accepting reservation payments without a documented custody, refund and KYC process.
  6. 6Using one generic CPCV for every buyer and unit.
  7. 7Treating every payment as non-refundable regardless of the document and cause of non-completion.
  8. 8Assuming buyer deposits are automatically protected.
  9. 9Ignoring the lender's sales controls — a signed buyer contract may not ensure release of the mortgage.
  10. 10Describing exclusive-use space as privately owned when the title classifies it as common property.
  11. 11Setting an artificially low condominium budget.
  12. 12Completing without an aftercare reserve.
  13. 13Opening an operating asset before commissioning is complete.
  14. 14Assuming a management agreement transfers operating risk.
  15. 15Calling the asset stabilised too early.
  16. 16Selecting an asset or share sale only by headline tax.
  17. 17Distributing proceeds before all liabilities are provided for.

Sales, operation and exit checklist

Before closing the development cycle, confirm that you have:

Progress: 0/47

Progress is saved in this browser only.

Frequently asked questions

Can units be marketed before construction is complete?

Potentially. The marketing must accurately describe the project's current status and should not present uncertain approvals, specifications, areas or completion dates as guaranteed. The buyer documentation must address the risks associated with a property that is under construction.

Does a reservation transfer ownership?

No. A reservation generally holds a commercial position for a limited period. Ownership normally transfers only through the legally required final transaction.

Does a CPCV transfer ownership?

Generally, no. A CPCV creates contractual obligations to enter the future transaction. Specific arrangements concerning real effect and registration may be possible if the legal requirements are satisfied.

Is every amount paid under a CPCV automatically a "sinal"?

The contract and circumstances must be reviewed. Portuguese law contains presumptions and consequences concerning amounts paid by a promissory buyer, but the intended treatment should be expressly documented.

Can the developer keep the deposit whenever the buyer does not complete?

Not automatically. The result depends on the CPCV, payment classification, cause of non-completion, notice and remedy procedure, consumer law and applicable Civil Code rules.

Are buyer deposits automatically held in escrow?

No. An escrow or equivalent protection requires a genuine legal and contractual arrangement, and the receiving account should be identified expressly.

Can the developer change the unit during construction?

Some changes may be contractually and legally possible. The effect depends on the reason, materiality, planning status, buyer contract, consumer rules and impact on area, use, specification and value.

Can the final sale proceed without exhibiting a use authorisation?

The current transfer formalities were altered by Decree-Law 10/2024, which removed the general requirement to exhibit or prove the use authorisation at the transfer. This does not confirm the property's lawful status or eliminate buyer, lender and contractual due diligence, and the rules change again under the revised RJUE scheduled to enter into force on 1 October 2026.

Must the building be in property horizontal before units are sold separately?

The required ownership and registration structure must be completed before an autonomous unit can be validly transferred as such. The timing and documents should be coordinated with the registry, lender and transaction professional.

Who is responsible for defects after a residential unit is sold?

The professional seller may have direct statutory responsibility to a consumer. The developer may separately have rights against the contractor, consultants, suppliers and insurers, but those supply-chain rights do not remove the seller's consumer obligations.

Can the developer transfer defect responsibility to the condominium?

Not generally for liabilities that remain legally or contractually those of the developer. The condominium manages common interests but should not be used to absorb the developer's construction obligations.

Can a tourist apartment be used as an ordinary home?

Not necessarily. Tourist units can be subject to compulsory tourist operation, operator control, owner-use restrictions and a specific constitutive title. The permitted use and tourist regime must be reviewed before marketing or acquisition.

Is an operator lease safer than a management agreement?

It allocates risk differently. A lease may provide more predictable rent but introduces operator-credit and lease-enforcement risk. Under a management agreement, the owner commonly retains more operating and working-capital risk.

When is an asset ready to refinance?

Normally when title, planning, construction and operational matters are acceptable to the lender and the property has sufficient value and sustainable income. The exact requirements depend on the financing.

Is a share sale always more tax-efficient than a property sale?

No. The outcome depends on company history, investor residence, asset value, tax basis, available exemptions, liabilities, financing and Portuguese real-estate-related tax rules.

Can all sale proceeds be distributed immediately?

Only after considering debt repayment, lender restrictions, corporate law, tax, project liabilities, warranty claims, reserves and the approved investor waterfall.

Tools for this phase

Sales and exit route selector

Compare unit sales, bulk sale, leasing, operation, refinancing and company sale before committing to a commercial route.

Choose the commercial route

Unit release and pricing planner

Organise inventory, prices, discounts, deposits, lender releases and completion dates in one controlled plan.

Build the sales plan

Completion and handover tracker

Coordinate title documents, buyer inspections, lender releases, deeds, keys and defects through to handover.

Track buyer completion

Development process complete

From opportunity to realised value

You have completed the development process from initial strategy and property assessment through acquisition, planning, finance, construction, commercialisation, operation and exit. The phases should not be treated as isolated steps: a decision made during acquisition can affect planning, planning affects design and construction, and construction affects sales, operation and finance. Return to the complete process whenever the project changes, a new investor or lender enters, planning is amended, costs increase, the commercial route changes or an exit is proposed.

Review the complete Development Process

Legal support through VVA

VVA can support investors, developers, family offices, funds, operators and landowners throughout commercialisation, operation and disposal: sales-strategy structuring, mediation agreements, reservations, CPCVs, bulk-sale agreements, property-horizontal documentation, condominium regulations, buyer due diligence and AML procedures, lender sales controls, mortgage-release coordination, completion and registration, buyer handover, consumer claims, defect coordination, residential and commercial leases, operator and franchise agreements, operational readiness, refinancing, asset and share sales, data rooms, disclosures, warranties and investor distributions.

Legal services are provided by Valente Veiga & Associados.

Official sources and further reading

  • Portuguese Civil Code.
  • Real estate mediation regime — Law 15/2013.
  • Anti-money-laundering legislation — Law 83/2017.
  • Consumer conformity regime — Decree-Law 84/2021.
  • General consumer-protection law.
  • General contractual-terms regime.
  • RJUE — Legal Framework for Urbanisation and Building.
  • Decree-Law 10/2024 — urban-planning simplification.
  • Decree-Law 108/2026 — revised RJUE.
  • Decree-Law 155-B/2026 — postponement to 1 October 2026.
  • Building energy-certification regime — Decree-Law 101-D/2020.
  • Tourist-development regime — Decree-Law 39/2008.
  • New Urban Lease Regime — NRAU.
  • Casa Pronta property and registration service.
  • Portuguese Corporate Income Tax Code.
  • Portuguese IMT Code.
  • Portuguese Stamp Duty Code.

Last reviewed: 21 August 2026

This page provides general information about the sale, leasing, operation, refinancing and disposal of real estate developments in Portugal. It does not constitute legal, tax, accounting, planning, consumer, tourism, investment, valuation, banking or financial advice. The applicable requirements depend on the property, planning history, ownership structure, buyer or tenant, project use, contract, financing, municipality, transaction date and legislation in force. Obtain project-specific professional advice before marketing property, accepting reservations or deposits, signing a CPCV or lease, transferring ownership, opening an operational asset, refinancing, selling a project company or distributing investment proceeds.