Planning & Design

Planning and design connect the investment case to the physical development. The objective is not simply to produce an attractive architectural proposal. It is to create a project that can be lawfully implemented, technically constructed, financed, operated and sold within the approved budget and programme.

05Planning & Design

At a glance

Indicative duration
8–24 months
The decision
At the end of this phase, you should be able to determine what can be designed within the applicable planning framework, what municipal procedure applies, whether the architectural solution supports the investment case, and whether the project is ready for procurement and construction.
Documents
  • Architectural project with the full technical set.
  • Specialist projects: structure, water, drainage, electrical, gas, acoustics, thermal, fire safety.
  • External opinions from the entities identified for the site.

The decision this phase helps you make

At the end of this phase, you should be able to determine what can be designed within the applicable planning framework, what municipal procedure applies, whether the architectural solution supports the investment case, and whether the project is ready for procurement and construction.

By the end of this phase, you should be able to determine:

  • what can be designed within the applicable planning framework;
  • what municipal procedure applies;
  • whether a Request for Prior Information, or PIP, should be submitted;
  • which approvals, consultations and sector-specific procedures are required;
  • whether the architectural solution supports the investment case;
  • whether the design is coordinated across all technical disciplines;
  • whether the project can be built within the approved budget;
  • whether the proposed phasing is legally and technically workable;
  • whether the project is ready for procurement and construction;
  • and which risks remain before works can lawfully begin.

Planning approval, design completion and construction readiness are different milestones. They should not be treated as interchangeable.

02Start with a written development brief

Before the design team produces a concept, the developer should issue a coordinated development brief.

The brief should define the project's:

  • Strategic purpose — build-to-sell, build-to-rent, hotel or tourism operation, serviced apartments, student accommodation, senior living, healthcare, offices, logistics, retail, mixed-use or another operating model.
  • Target market — intended buyers or users, target price or rental range, expected unit mix, minimum product standards, accessibility requirements, service expectations and relevant international or operator standards.
  • Development parameters — permitted use, construction area, footprint, height, number of floors, number of units, parking, external areas, landscaping, common facilities, technical areas, infrastructure and development phasing.
  • Commercial parameters — target saleable or lettable area, target revenue, maximum construction cost, professional fees, planning and infrastructure costs, contingency, finance assumptions, target completion date and minimum return.
  • Sustainability and performance — energy performance, water consumption, embodied carbon, operational carbon, materials, resilience, mobility, landscape, biodiversity, waste, building certification and long-term maintenance.
  • Operational requirements — for an operating asset, the requirements of the intended operator, manager, franchise or brand, which may affect room or unit sizes, circulation, kitchens, back-of-house areas, servicing, loading, staff facilities, fire strategy, security, acoustics, technical systems and maintenance access.

A brief that is not commercially and operationally validated can produce a licensable project that does not support the investment case.

03Build the right project team

The required team depends on the scale, use, complexity and location of the project.

Key roles include:

  • Developer or project owner — defines investment objectives, approves the budget and makes the principal project decisions.
  • Development manager — coordinates the business plan, design, licensing, procurement and delivery strategy.
  • Project manager — controls programme, responsibilities, deliverables, meetings, decisions, dependencies, reporting and change management.
  • Lead architect — develops the architectural concept and coordinates its integration with planning, engineering and operational requirements.
  • Planning and legal advisers — assist with interpretation of territorial plans, urban-planning procedures, administrative precedents, title and development rights, municipal requirements, external consultations and contractual appointments.
  • Engineering team — structural, water and drainage, electricity, telecommunications, gas, mechanical systems, HVAC, energy and thermal performance, acoustics, fire safety, lifts and vertical transport, roads and infrastructure, and specialist installations.
  • Survey and investigation team — topographical surveyor, cadastral specialist, geotechnical engineer, environmental consultant, structural surveyor, utilities surveyor, archaeologist and contamination specialist.
  • Cost consultant — tests the design against the approved budget at every stage.
  • Landscape architect — affects planning integration, open space, water management, fire resilience, biodiversity, visual impact and value.
  • Sustainability consultant — translates environmental objectives into measurable design requirements and assesses cost and operational consequences.
  • Operator and commercial advisers — hotels, tourism, healthcare, senior living, logistics and other operational developments should involve the operator or specialist adviser early.

Professional qualifications and responsibility

Projects, construction management and supervision functions must be performed and signed by professionals legally qualified for the relevant activity.

The applicable qualification framework should be checked for the project type, building category, complexity, professional discipline and specific act to be performed.

The appointment of a qualified professional does not remove the developer's responsibility to establish a coordinated project-management and quality-control system.

Terms and declarations of responsibility have legal significance. They should not be treated as administrative formalities.

Portugal's professional qualification framework is principally established by Law 31/2009, as amended, including by Law 3/2026.

04Establish the verified project baseline

The design team should not begin from unverified drawings or seller information.

The baseline should include, as applicable:

  • current land registry information;
  • tax registration information;
  • confirmed site boundaries;
  • topographical survey;
  • cadastral information;
  • existing building surveys;
  • the last valid municipal record;
  • approved drawings;
  • use titles or other evidence of lawful use;
  • existing licences, communications and prior information decisions;
  • applicable territorial plans;
  • allotment or subdivision documents;
  • easements and public-law restrictions;
  • infrastructure records;
  • utilities capacity;
  • geotechnical information;
  • environmental constraints;
  • heritage and archaeological information;
  • operator requirements;
  • and the acquisition assumptions.

Discrepancies should be resolved before they are incorporated into the design. An inaccurate boundary, incorrect building record or invalid assumption about the lawful existing condition can affect the entire project.

05The planning and design sequence

The phase moves from a written brief through constraints, concept, validation, planning strategy, architectural and specialist development, and finally into detailed design and procurement information.

Stage 1 — Project brief

Translate the business plan into measurable design requirements. Outputs include the approved development brief, area schedule, unit or use mix, operational requirements, cost limit, sustainability targets, programme and decision-making structure.

+Show details(7)

Stage 2 — Constraints and requirements matrix

Map the rules and conditions affecting the project. The matrix should identify territorial plans, land-use rules, construction parameters, easements, public-law restrictions, heritage, access, infrastructure, parking, fire safety, accessibility, environmental requirements, sector-specific rules and external authorities.

Outputs: constraints plan, planning parameters schedule, consultation list, risk register and preliminary procedural route.

Stage 3 — Concept and massing

Test different physical responses to the brief. The concept stage should compare site layout, building footprint, massing, height, orientation, access, servicing, parking, public and private areas, landscape, unit mix, saleable area, technical areas and construction approach.

Outputs: concept alternatives, massing study, preliminary area schedule, planning compliance assessment, preliminary cost plan and preferred option.

Stage 4 — Commercial and technical validation

Before selecting the final concept, update development revenue, construction cost, planning risk, infrastructure cost, phasing, operational performance, sales or leasing assumptions, financing requirements and return. The preferred design should be selected because it creates the best risk-adjusted outcome, not simply because it maximises theoretical construction area.

Stage 5 — Planning strategy

Determine whether the project should proceed through a Request for Prior Information, licensing, prior communication, an applicable exemption from municipal control, a subdivision or allotment operation, an urbanisation works procedure, a change-of-use procedure or a combination of procedures.

The correct route depends on the operation, site, plans, previous urban operation, existing title and legislation in force on the submission date.

Stage 6 — Architectural project

Develop the preferred concept into a compliant architectural proposal. The architectural project should coordinate external design, urban and landscape integration, internal layouts, circulation, accessibility, fire strategy, parking, refuse, servicing, technical spaces, structural grid, façades, roofs and applicable construction requirements.

Stage 7 — Specialist engineering projects

Develop the technical systems required to construct and operate the development. Architecture and engineering must be coordinated before submission and before procurement.

Stage 8 — Detailed design and procurement information

Convert the approved design into coordinated construction and pricing information. Depending on the procurement model, this may include detailed drawings, specifications, schedules, bills of quantities, performance requirements, interface matrices, approved material standards, mock-up requirements, BIM deliverables and contractor design responsibilities.

06Request for Prior Information — PIP

A Request for Prior Information, commonly called a PIP, asks the municipality to provide a formal position on the feasibility or applicable conditions of a proposed urban operation.

A PIP can be particularly valuable when:

  • the planning interpretation is uncertain;
  • the acquisition remains conditional;
  • the project involves material planning risk;
  • the land is being marketed on the basis of unconfirmed development capacity;
  • external authorities must be consulted;
  • the project is intended to be sold before full licensing;
  • or the investor requires greater certainty before committing further capital.

A PIP must ask the right question

A favourable answer is only valuable to the extent that the request clearly defines the intended project. Depending on the applicable regime and desired level of certainty, the PIP may address use, construction area, footprint, height, number of floors, number of units, access, parking, infrastructure, external areas, demolition, urbanisation works, phasing and other relevant parameters.

A vague PIP may produce a response that is formally favourable but commercially insufficient.

Legal effect

Under the regime applicable before the entry into force of the amendments introduced by Decree-Law 108/2026, a favourable PIP can bind the competent authorities within the terms and limits of the decision.

The favourable information is subject to statutory validity periods. Under the current framework, the relevant subsequent procedure should generally be initiated within two years, with a possible additional period where the legal requirements are met.

From 1 October 2026, Decree-Law 108/2026 introduces a revised distinction between different levels of PIP. A favourable PIP containing all the legally required detailed parameters may, when the statutory conditions are met, exempt the corresponding operation from a subsequent licence or prior communication, provided that the operation is executed exactly as assessed.

The precise legal effect must be verified against the legislation in force on the submission date, the content of the request, the municipal decision, the parameters covered, external consultations, validity periods and any subsequent design changes. A PIP is not an unrestricted guarantee that any later version of the project will be accepted.

07Licensing, prior communication or exemption?

The Portuguese RJUE establishes different procedural routes for urban operations.

Licensing

Licensing involves a formal municipal decision. Depending on the procedure, the architectural project may be assessed before the specialist engineering projects and other studies are delivered. A favourable architectural decision does not, by itself, mean that construction can begin. The project must still complete the remaining procedural, technical, payment, title and commencement requirements.

+Show details(3)

Prior communication

Prior communication applies where the statutory conditions for that route are satisfied. It places substantial responsibility on the developer, project authors, technical coordinators, construction professionals and other persons signing the required declarations. A submission does not protect an unlawful project merely because the municipality has not intervened before work begins. Municipal inspection and enforcement powers remain applicable.

Exemption from municipal control

Certain works may be exempt from licensing or prior communication. An exemption does not mean that technical, planning, heritage, safety or other legal rules cease to apply. The developer should document the legal basis for the exemption, the project assessed, the professionals responsible, any required terms of responsibility, applicable fees, external permissions and any information that must be submitted before works begin.

Communication prior to use

The procedure applicable to the use of a completed building or unit depends on the works performed and the legal regime in force at the relevant time. The developer should plan the use-title documentation before construction begins. Completion documentation, responsibility terms, certificates and as-built information should be identified in the project execution plan.

Architecture approval is not construction approval. A municipal decision approving the architectural project generally confirms only the matters legally assessed at that stage. The developer may still need to complete specialist projects, external consultations, sector-specific approvals, municipal fees, infrastructure arrangements, contractor appointment, construction-professional appointments, commencement information, insurance, guarantees and other statutory requirements. Do not instruct a contractor to mobilise solely because the architecture has been approved.

08Specialist engineering projects

Depending on the development, specialist projects may include structural stability, excavation and retaining structures, water supply, wastewater and stormwater drainage, electricity, telecommunications, gas, mechanical ventilation, heating and cooling, thermal and energy performance, acoustics, fire safety, lifts and vertical transport, roads, parking systems, landscape irrigation, waste systems, renewable energy and external infrastructure.

Under the simplification measures introduced in 2024, municipalities do not generally perform prior technical approval of the internal specialist engineering solutions in the same manner as the architectural and planning assessment.

Specialist projects are supported by responsibility declarations signed by qualified professionals. This does not reduce the obligation to comply with the applicable legislation. It also does not eliminate professional liability, external approvals legally required for particular systems, certification, inspections, contractor responsibility, municipal enforcement or the developer's need for independent quality control.

The absence of detailed municipal technical review should not be treated as proof that the specialist design is correct or coordinated.

09External consultations and sector-specific approvals

A municipal procedure may require input from external authorities because of the project's location, use, environmental impact, heritage context, infrastructure, road access, proximity to water, protected landscape, aviation constraints, tourism classification, fire risk, healthcare use or other regulated characteristics.

Relevant entities may include, depending on the project:

  • territorial coordination authorities;
  • environmental authorities;
  • heritage authorities;
  • road authorities;
  • water and utilities entities;
  • tourism authorities;
  • civil-protection or fire-safety authorities;
  • health authorities;
  • and infrastructure concessionaires.

Some consultations are promoted within the municipal procedure. Others may have to be obtained directly by the applicant or through a separate legal procedure. The team should establish which entities must be consulted, who initiates each consultation, what information is required, whether the opinion is binding, its validity period and whether a project amendment requires renewed consultation.

10Design for planning, construction and operation

A successful project must satisfy three different tests.

The project must pass:

  • Planning compliance — can the project be lawfully approved or carried out under the applicable planning framework?
  • Construction viability — can the project be built safely, efficiently and within the approved budget and programme?
  • Operational and commercial performance — will the completed development meet the requirements of buyers, tenants, operators, lenders and investors?

A project that passes only one or two of these tests is not ready to proceed.

11Area definitions must be controlled

Development projects frequently use multiple area measurements. These may include site area, footprint, total construction area, gross floor area, saleable area, lettable area, private area, common area, technical area, external covered area, balconies and terraces, and areas counted differently for planning, tax, valuation or sales purposes.

The project should maintain a controlled area schedule defining:

  • each measurement;
  • the applicable standard;
  • included and excluded areas;
  • source drawing;
  • design version;
  • and responsible person.

Planning area, construction area and saleable area should never be assumed to be identical. An error in area definitions can affect planning compliance, purchase price, construction cost, revenue, finance, valuation, marketing and sale documentation.

12Existing buildings and rehabilitation projects

Projects involving existing buildings require additional investigation. Confirm the lawful existing condition, the last valid municipal record, authorised use, historic alterations, unlicensed works, structural condition, heritage restrictions, retained façades or elements, party walls, existing easements, access, fire strategy, accessibility, seismic requirements, energy performance and the technical feasibility of the proposed use.

Do not assume that the building's physical condition corresponds to the approved municipal drawings. Where discrepancies exist, determine whether they can be:

  • accepted as lawful;
  • documented;
  • corrected;
  • licensed;
  • legalised;
  • demolished;
  • or incorporated into the new project.

A new project should not be designed on top of an unresolved unlawful condition.

13Tourism and hospitality projects

Hotels, tourist apartments, resorts and other tourism developments require coordination between urban planning, tourism legislation, classification requirements, operator standards, fire safety, accessibility, health and hygiene, food and beverage, leisure facilities and operational licensing or registration.

The intended tourism category and operating model should be defined before the design is fixed. Late operator involvement can require expensive changes to:

  • room dimensions;
  • back-of-house areas;
  • kitchens;
  • staff circulation;
  • lifts;
  • plant;
  • storage;
  • waste;
  • loading;
  • reception;
  • leisure facilities;
  • and fire compartmentation.

Urban permission to construct a building does not, by itself, confirm that the completed asset can lawfully operate under the intended tourism model.

14Loteamento and urbanisation works

Larger developments may require an allotment or subdivision operation, urbanisation works or another territorial implementation mechanism. These can involve creation of plots, roads, pedestrian areas, parking, public spaces, green areas, utility networks, municipal transfers, infrastructure reinforcement, compensation payments, guarantees, public consultation and phased reception of works.

The development model should establish:

  • which land remains private;
  • which areas are transferred;
  • which infrastructure is built by the developer;
  • who owns and maintains it;
  • the applicable guarantees;
  • completion and reception procedures;
  • and the effect of phasing on building construction and sales.

Infrastructure cost and timing can materially change the feasibility of the entire project.

15Design coordination

Every project should have a documented coordination process.

Design responsibility matrix

Identify who is responsible for each drawing, each specification, each calculation, each legal requirement, each interface and each submission.

+Show details(3)

Common design platform

Maintain a controlled system containing current drawings, superseded versions, models, specifications, schedules, surveys, authority correspondence, decisions and approval status.

Coordination reviews

Review interfaces between architecture and structure, architecture and building services, structure and underground infrastructure, façades and waterproofing, landscape and drainage, fire strategy and circulation, accessibility and level changes, operator requirements and technical systems, and design and construction sequencing.

Design freeze

Define when the project reaches concept freeze, planning freeze, tender freeze and construction freeze. A design freeze does not prevent all changes. It establishes that further changes require formal approval and an assessment of cost, programme, planning and contractual impact.

16BIM and digital coordination

Building Information Modelling can assist with multidisciplinary coordination, clash detection, quantity extraction, change control, asset information and construction sequencing.

BIM does not correct an incomplete brief or unclear contractual responsibility. The required models, detail levels, ownership, permitted uses and delivery formats must be defined in the appointments.

17Cost control during design

Cost planning should run in parallel with design. At each stage, compare the project against approved construction cost, infrastructure cost, professional fees, municipal charges, finance cost, contingency, revenue and return.

Concept cost plan

Tests whether the initial massing and product assumptions remain viable.

+Show details(4)

Planning-stage cost plan

Reflects the architectural proposal submitted or intended for submission.

Coordinated design cost plan

Includes the developing engineering systems and identified site conditions.

Pre-tender estimate

Tests the coordinated procurement information before contractor pricing.

Tender reconciliation

Compares contractor proposals on a common basis and identifies omissions, qualifications and risk allowances.

Value engineering should improve the balance between cost, function, quality and risk. It should not be a late exercise that removes essential performance or creates licensing and coordination problems.

18Design changes

Every material change should be assessed for its effect on planning compliance, existing approvals, external consultations, structural design, fire safety, accessibility, energy, acoustics, infrastructure, construction cost, programme, procurement, finance, operator requirements and sales commitments.

Changes to an approved or submitted project may require:

  • a revised municipal procedure;
  • an amendment;
  • prior communication;
  • further information;
  • updated responsibility declarations;
  • renewed external consultation;
  • or post-completion legalisation.

A change is not legally immaterial merely because it appears minor from a commercial perspective.

19Preparing for procurement and construction

Before the project enters procurement or construction, confirm that the documentation is sufficient for the chosen delivery model. The package may need to include coordinated architectural drawings, coordinated engineering drawings, specifications, schedules, finishes, performance criteria, scope boundaries, employer's requirements, interface matrix, quantity information, construction programme assumptions, phasing, logistics, temporary works requirements, quality-control procedures, mock-ups, commissioning requirements, completion deliverables and as-built information requirements.

Unresolved design should be identified expressly. If part of the design is delegated to the contractor, define:

  • the delegated scope;
  • performance standard;
  • approval procedure;
  • design liability;
  • professional qualifications;
  • insurance;
  • coordination responsibility;
  • and ownership of the resulting documents.

20Planning and design cost categories

The budget may need to include architects, engineers, planning consultants, legal advisers, project management, development management, cost consultancy, topographical survey, cadastral work, geotechnical investigation, environmental studies, structural surveys, heritage and archaeological studies, fire engineering, accessibility advice, sustainability consultancy, operator or sector consultants, BIM management, models and visualisations, municipal fees, external authority charges, infrastructure studies and contingency for design changes.

Professional fees should be linked to:

  • scope;
  • deliverables;
  • project stages;
  • programme;
  • number of revisions;
  • meetings;
  • coordination duties;
  • submission responsibility;
  • construction support;
  • and completion documents.

A low initial fee may become expensive if the appointment excludes essential coordination or construction-stage services.

The planning and design decision gate

Proceed to structure, finance and delivery only when the following questions can be answered.

  • Planning — Is the intended use permitted?
  • Planning — Are the principal construction parameters confirmed?
  • Planning — Is the correct municipal procedure identified?
  • Planning — Are external consultations mapped?
  • Planning — Is any favourable PIP still valid and applicable to the current design?
  • Planning — Are allotment, urbanisation or infrastructure obligations understood?
  • Design — Does the design comply with the approved brief?
  • Design — Are architecture and engineering coordinated?
  • Design — Are areas consistently defined?
  • Design — Are accessibility, fire, energy, acoustic and operational requirements integrated?
  • Design — Are the drawings based on verified site and building information?
  • Commercial — Does the current area schedule support the revenue assumptions?
  • Commercial — Is the project within the cost limit?
  • Commercial — Are infrastructure and technical-area requirements included?
  • Commercial — Has operator or market feedback been incorporated?
  • Commercial — Is the project still capable of achieving the target return?
  • Delivery — Is the project sufficiently developed for the selected procurement route?
  • Delivery — Are contractor-design responsibilities defined?
  • Delivery — Is the phasing workable?
  • Delivery — Can the project lawfully proceed within the required programme?
  • Delivery — Are design changes controlled?
  • Documentation — Is there a controlled set of current documents?
  • Documentation — Are authority decisions and conditions recorded?
  • Documentation — Are professional appointments complete?
  • Documentation — Are intellectual-property and file-use rights secured?
  • Documentation — Is the next submission or commencement package clearly defined?

If any critical answer remains uncertain, the project should not move into irreversible procurement or construction commitments.

Red flags at this phase

  • Designing before verifying the planning framework.
  • Maximising area without testing commercial efficiency.
  • Treating a PIP as a generic confirmation.
  • Assuming architectural approval allows construction to begin.
  • Assuming that specialist projects are approved by the municipality.
  • Ignoring the legislative transition around 1 October 2026.
  • Assuming that the RGEU has been repealed.
  • Appointing disciplines too late.
  • Using inconsistent area definitions.
  • Failing to verify the lawful existing condition.
  • Submitting an uncoordinated project.
  • Freezing the commercial model too late.
  • Leaving design responsibility unclear.

Indicative timing

Planning and design periods vary significantly by project. As an initial planning assumption:

Typical durations include:

  1. project brief and team mobilisation: 2–4 weeks;
  2. surveys and baseline investigations: 3–10 weeks;
  3. concept and massing: 4–10 weeks;
  4. feasibility validation: 2–4 weeks;
  5. PIP preparation: 4–12 weeks;
  6. municipal PIP procedure: several months, depending on consultations and complexity;
  7. architectural project: 3–8 months;
  8. municipal licensing procedure: dependent on the procedure, completeness and external consultations;
  9. specialist engineering: 2–6 months;
  10. detailed design and procurement information: 3–8 months.

These activities may overlap. Statutory municipal decision periods are not equivalent to the total end-to-end programme. The programme must also allow for preparation, surveys, external consultations, corrections, public consultation, fees, project-team responses, finance, procurement and transitional legislative requirements.

Common planning and design mistakes

  1. 1Designing before verifying the planning framework — an attractive concept has limited value if it conflicts with the applicable plan, restrictions or infrastructure capacity.
  2. 2Maximising area without testing commercial efficiency — more construction area can produce higher cost, inefficient layouts, increased parking and infrastructure obligations, or lower product quality.
  3. 3Treating a PIP as a generic confirmation — a favourable PIP only protects the parameters and proposal actually assessed within its legal scope and validity period.
  4. 4Assuming architectural approval allows construction to begin — further projects, documents, fees, titles and commencement requirements may remain outstanding.
  5. 5Assuming that specialist projects are approved by the municipality — professional responsibility and technical compliance remain with the qualified project authors and other responsible parties.
  6. 6Ignoring the legislative transition — the applicable RJUE procedure may depend on whether the submission occurs before or after 1 October 2026.
  7. 7Assuming that the RGEU has been repealed — its repeal has been deferred until the replacement technical building legislation enters into force.
  8. 8Appointing disciplines too late — late structural, fire, mechanical, operator or cost input can require substantial redesign.
  9. 9Using inconsistent area definitions — different area measurements can distort planning, cost, valuation, finance and revenue assumptions.
  10. 10Failing to verify the lawful existing condition — physical construction does not prove that an existing building or alteration is legally authorised.
  11. 11Submitting an uncoordinated project — conflicts between architecture and engineering create delays, variations and construction claims.
  12. 12Freezing the commercial model too late — changes to unit mix, operation or specification after planning submission may require redesign or procedural amendments.
  13. 13Leaving design responsibility unclear — missing or overlapping responsibility creates gaps that often emerge only during construction.

Planning and design checklist

Before moving to the next phase, confirm that you have:

Progress: 0/29

Progress is saved in this browser only.

Frequently asked questions

Should every project start with a PIP?

No. A PIP is most useful where material planning uncertainty exists or where formal confirmation is required before acquisition, finance or full design expenditure. A project with clear and sufficiently defined planning parameters may proceed directly through the applicable route.

Does a favourable PIP guarantee a construction licence?

It can bind the competent authorities within the parameters, legal effects and validity period applicable to the particular PIP. It does not protect a materially different project or eliminate the need to comply with conditions and technical requirements. From 1 October 2026, a sufficiently detailed favourable PIP may have additional effects under Decree-Law 108/2026.

How long does a PIP remain effective?

The applicable regime generally provides a two-year period for the relevant subsequent action, with the possibility of a further period where the statutory requirements are met. The exact deadline should be calculated from the notification or legally relevant formation of the favourable decision and verified against the legislation applicable to the procedure.

Can construction begin after approval of the architectural project?

Not solely on that basis. The remaining procedural requirements, specialist projects, fees, construction title, contractor information, technical appointments and commencement requirements must be completed.

Does the municipality approve the specialist engineering projects?

Under the current simplification framework, municipalities do not generally undertake prior approval of the internal technical solutions covered by qualified professionals' responsibility declarations. However, the projects must comply with the law, and external approvals, certifications, inspections or sector-specific requirements may still apply.

Can we choose between licensing and prior communication?

Not freely in every case. The applicable procedure is determined by the legislation, planning framework, prior urban operation and characteristics of the proposed works. The route should be legally confirmed before submission.

Does exemption from municipal control mean that no rules apply?

No. An exempt operation must still comply with all applicable planning, construction, safety, heritage and technical rules. Other authorisations, responsibility declarations, information duties or fees may also apply.

Has the RGEU been repealed?

No. Its repeal was deferred and is intended to take effect when the future legislation defining the replacement technical building standards enters into force.

What changes on 1 October 2026?

Decree-Law 108/2026 is scheduled to introduce substantial changes to the RJUE, including the procedural treatment of PIPs, licensing, prior communications, urban titles, use of buildings and municipal procedures. Each project should be reassessed before any submission made on or after that date.

Can the approved design be changed during construction?

Changes may be possible, but their legal and contractual treatment depends on their nature and impact. A change may require a prior amendment, communication, updated project, revised terms of responsibility or further consultation. The procedure must be confirmed before the altered work is executed.

Does municipal silence mean the project is automatically safe to build?

No. Portuguese law provides tacit approval mechanisms in certain procedures and circumstances, but their formation, proof, scope and effects must be legally confirmed. Silence should never be treated as informal permission.

Should the contractor complete the detailed design?

The contractor may develop defined parts of the design if the procurement documents allocate that responsibility clearly. The developer must specify the performance requirements, approvals, professional qualifications, liability, coordination and intellectual-property arrangements.

Tools for this phase

Planning Route Selector

Identify whether the project may require a PIP, licence, prior communication or another procedure.

Check the planning route

PIP Scope Builder

Define the use, area, height, units, access, parking and infrastructure parameters to include in a PIP.

Build your PIP scope

Design Team Builder

Identify the professional disciplines required for the project.

Build the project team

Area Schedule Tool

Compare planning, construction, saleable, lettable, private, common and technical areas.

Build the area schedule

Design Coordination Tracker

Record project interfaces, responsibilities, outstanding decisions and document status.

Track design coordination

Planning Programme Builder

Create a project timeline covering surveys, design, consultations, submissions and decisions.

Build the planning programme

Next phase

06 — Structure & Finance

Build the ownership, investment, tax and financing structure required to fund and deliver the project. The next phase explains how to coordinate the development company, investor capital, shareholder arrangements, senior debt, security, drawdowns, cost overruns and financial controls.

Continue to Structure & Finance

Legal support through VVA

VVA can support investors, developers, family offices, funds and operators throughout the planning and design phase of Portuguese real estate developments. Support may include planning and legal due diligence, interpretation of municipal plans and administrative precedents, definition of the urban-planning procedure, preparation and review of PIP strategies, coordination with architects and planning consultants, review of municipal decisions and conditions, external-authority procedures, professional appointments, design and intellectual-property provisions, operator and consultant agreements, infrastructure and urbanisation arrangements, development phasing, planning-related acquisition conditions, management of project amendments and preparation for procurement, finance and construction.

Legal services are provided by Valente Veiga & Associados.

Official sources and further reading

  • RJUE — Legal Framework for Urbanisation and Building
  • Decree-Law 10/2024 — urban-planning simplification measures
  • Decree-Law 108/2026 — revision of the RJUE
  • Decree-Law 155-B/2026 — postponement to 1 October 2026
  • Portaria 71-A/2024 — documents required for RJUE procedures
  • Law 31/2009 — qualifications of project and construction professionals
  • Law 3/2026 — amendment to the professional qualification framework
  • General Regulation for Urban Buildings — RGEU
  • RJIGT — territorial management instruments
  • National Territorial Information System — SNIT

Last reviewed: 21 August 2026

This page provides general information about planning, design and urban procedures in Portugal. It does not constitute legal, planning, architectural, engineering, tax, investment or financial advice. The applicable procedure and requirements depend on the location, property, planning instruments, project, use, submission date and transitional legislation. Obtain project-specific professional advice before acquiring land, submitting a PIP, filing an urban-planning procedure, commencing works or relying on any approval, exemption, communication or tacit decision.